855 Castro St
San Francisco permit 201910043560 · Noe Valley
Legalization of exterior deck & construction of 14'-0" by 7'-6" long fire wall.adding an exterior grade 1 hour wall to the north side fo the yard to protect the deck at the second level.to comply w/ nov# 201960641.
- Filed
- Oct 4, 2019
- Issued
- Oct 3, 2022 (36 months after filing)
- Completed
- Jan 31, 2023 (4 months after issuance)
- Review stops
- 12 stops across 2 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Jul 25, 2019 | Jul 25, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2019 | Oct 4, 2019 | — |
Zoning review Planning · CP-ZOC | Oct 4, 2019 | Apr 7, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 11, 2020 | Apr 7, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2020 | Dec 2, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 2, 2020 | Oct 3, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 7, 2021 | Apr 21, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 15, 2022 | Feb 23, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 13, 2022 | Apr 19, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2022 | Oct 3, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 18, 2022 | Aug 25, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 18, 2022 | Aug 23, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $14,600
| Name | Role | License on permit |
|---|---|---|
| David A Kesler David Kesler Architect | Architect | C28122 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023