43 07th Av
San Francisco permit 201910073693 · Inner Richmond
Erect a 4 stories, 1 dwelling, no basement, type 5, bldg.
- Filed
- Oct 7, 2019
- Issued
- Jan 14, 2022 (27 months after filing)
- Completed
- Not completed yet
- Review stops
- 46 stops across 6 departments
- Comments issued
- 13 times, by Permit Center, Building Inspection, Fire Department, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 10, 2019 | Oct 10, 2019 | — |
Zoning review Planning · CP-ZOC | Oct 10, 2019 | Feb 19, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Dec 18, 2020 | Dec 23, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 22, 2021 | Nov 30, 2021 | — |
Fire prevention review Fire Department · SFFD | May 3, 2021 | Jun 22, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 22, 2021 | Jun 29, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 30, 2021 | Oct 12, 2021 | — |
Zoning review Planning · CP-ZOC | Nov 30, 2021 | Dec 3, 2021 | — |
Fire prevention review Fire Department · SFFD | Dec 6, 2021 | Dec 8, 2021 | — |
Fire prevention review Fire Department · SFFD | Dec 6, 2021 | Dec 17, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 8, 2021 | Dec 14, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2021 | Dec 16, 2021 | — |
Development fee collection Building Inspection · DFCU | Dec 20, 2021 | Dec 20, 2021 | — |
Permit Processing Center Building Inspection · PPC | Dec 20, 2021 | Dec 20, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2021 | Jan 14, 2022 | — |
Addendum 1: Foundation,superstructure,t24,mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 22, 2024 | Mar 1, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 26, 2024 | Feb 26, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 29, 2024 | Feb 29, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Mar 1, 2024 | Mar 1, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 24, 2024 | Apr 2, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 25, 2024 | Mar 25, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 26, 2024 | Mar 26, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 2, 2024 | Apr 2, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jul 16, 2024 | Jul 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2024 | Aug 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 15, 2024 | Aug 28, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2024 | Aug 30, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 15, 2024 | Sep 3, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2024 | Aug 19, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2024 | Aug 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 15, 2024 | Aug 16, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 15, 2024 | In progress | — |
Urban forestry Public Works · DPW-BUF | Aug 19, 2024 | Sep 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 15, 2025 | Jan 15, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 25, 2025 | Apr 14, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2025 | Mar 27, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 25, 2025 | Apr 7, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 25, 2025 | Mar 27, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 25, 2025 | Apr 24, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 25, 2025 | Mar 31, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 25, 2025 | Mar 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,628,000
| Name | Role | License on permit |
|---|---|---|
| Robert Mark Baum Gould Evans Baum Thornley | Architect | C12094 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2014