365 Toni Stone Cg
San Francisco permit 201910073784 · Mission Bay
Proj-19-0275. mayor dir# 17-02. mou proj port of sf. priority processing. (building f) to erect 23 stories, 1 basementm, type i-a, 258 residential units with retail, office, restaurant, assembly, mix use (r-2,m,b,a-2,a-3)
- Filed
- Oct 7, 2019
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 94 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department
- Put on hold
- 15 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 9, 2019 | Oct 9, 2019 | — |
Fire Department SFFD-PRT | Oct 9, 2019 | Mar 3, 2020 | — |
Building plan review Building Inspection · BLDG | Oct 9, 2019 | Feb 21, 2020 | — |
Building plan review Building Inspection · BLDG | Nov 21, 2019 | Feb 21, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2019 | Jun 17, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2019 | May 12, 2020 | — |
Zoning review Planning · CP-ZOC | May 13, 2020 | Jun 16, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jun 18, 2020 | Mar 14, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 26, 2020 | Oct 26, 2020 | — |
Building plan review Building Inspection · BLDG | Dec 30, 2021 | Jan 24, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 25, 2022 | Mar 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 7, 2022 | Mar 3, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2022 | Feb 11, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 11, 2022 | Feb 15, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 22, 2022 | Feb 28, 2022 | — |
Fire Department SFFD-PRT | Mar 3, 2022 | Mar 3, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2022 | Mar 3, 2022 | — |
Addendum 1: Foundation & underground utilities.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 6, 2020 | Aug 6, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 7, 2020 | Mar 22, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Oct 22, 2020 | Nov 4, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Nov 9, 2020 | Mar 22, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 23, 2022 | Mar 23, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 23, 2022 | May 3, 2022 | — |
Addendum 2: Superstructure.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 15, 2022 | Mar 15, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 16, 2022 | Sep 12, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 13, 2022 | May 31, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2022 | Sep 14, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 14, 2022 | Sep 22, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 30, 2022 | Sep 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 9, 2023 | May 9, 2023 | — |
Addendum 3: Architectural & mep.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 8, 2022 | Sep 8, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 9, 2022 | Feb 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2022 | Apr 13, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Sep 9, 2022 | Apr 13, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 9, 2022 | Sep 12, 2022 | — |
Fire Department SFFD-PRT | Sep 12, 2022 | Apr 19, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Oct 17, 2022 | Oct 26, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2022 | Oct 25, 2022 | — |
Plumbing plan check Building Inspection · PID-PC | Oct 25, 2022 | Oct 27, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 26, 2022 | Nov 28, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2023 | Apr 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 19, 2023 | Apr 24, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 27, 2023 | Apr 28, 2023 | — |
Plumbing plan check Building Inspection · PID-PC | May 1, 2023 | May 5, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 5, 2023 | May 31, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 8, 2023 | May 9, 2023 | — |
Addendum 4: Exterior skin (curtain wall).
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 3, 2023 | Aug 3, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 3, 2023 | Aug 8, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 3, 2023 | Aug 21, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 3, 2023 | Aug 7, 2023 | Approved |
Fire Department SFFD-PRT | Aug 3, 2023 | Aug 24, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 1, 2024 | Apr 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2024 | Apr 8, 2024 | Approved-Stipulated |
Fire Department SFFD-PRT | Apr 9, 2024 | Apr 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2024 | Apr 12, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Apr 12, 2024 | Apr 18, 2024 | Administrative |
Addendum 7: Steel stairs.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2023 | Mar 10, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 10, 2023 | Apr 3, 2023 | — |
Fire Department SFFD-PRT | Mar 10, 2023 | May 2, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 3, 2023 | May 3, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 4, 2023 | May 4, 2023 | — |
Addendum 8: Generator & fuel oil.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 3, 2023 | Mar 3, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 3, 2023 | Oct 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2023 | Mar 23, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 3, 2023 | Mar 23, 2023 | — |
Fire Department SFFD-PRT | Mar 17, 2023 | Nov 2, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 20, 2023 | Oct 23, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 23, 2023 | Oct 23, 2023 | Approved |
Fire Department SFFD-PRT | Nov 29, 2023 | Nov 29, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 30, 2023 | Dec 22, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2023 | Dec 1, 2023 | Administrative |
Addendum 11: Window washing (bmu).
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 19, 2023 | Apr 19, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 19, 2023 | Aug 24, 2023 | Approved |
Fire Department SFFD-PRT | May 8, 2023 | Sep 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2023 | May 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2023 | Sep 12, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2023 | Sep 22, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Sep 22, 2023 | Sep 22, 2023 | Administrative |
Addendum 12: Interior code required signage.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 20, 2023 | Nov 20, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Nov 20, 2023 | Jan 10, 2024 | — |
Building plan review Building Inspection · BLDG | Nov 21, 2023 | Dec 20, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 21, 2023 | Dec 1, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 8, 2024 | Jan 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2024 | Jan 11, 2024 | Administrative |
Addendum 13: Storefront & misc exterior elements
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 3, 2024 | Jun 13, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 5, 2024 | Jun 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2024 | Jun 13, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 13, 2024 | Jun 17, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jun 13, 2024 | Dec 13, 2024 | Administrative |
Fire Department SFFD-PRT | Jun 20, 2024 | Jul 22, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 21, 2024 | Dec 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 20, 2024 | Nov 22, 2024 | Approved |
Fire Department SFFD-PRT | Dec 12, 2024 | Dec 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2024 | Jan 28, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Approved
- Estimated cost
- $99,907,840
| Name | Role | License on permit |
|---|---|---|
| Jeanne K Gang | Architect | C34329 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026