2435 21st Av
San Francisco permit 201910083802 · Sunset/Parkside
Per adu ordinance# 95-17, add adu @ the rear of the building. 2 bedroom & 3 bathrooms.
- Filed
- Oct 8, 2019
- Issued
- Feb 25, 2022 (29 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 15, 2019 | Oct 15, 2019 | — |
Zoning review Planning · CP-ZOC | Oct 16, 2019 | Sep 23, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Jul 9, 2020 | Jul 31, 2020 | — |
Building plan review Building Inspection · BLDG | Oct 1, 2020 | Mar 10, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 6, 2020 | Mar 18, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 19, 2021 | Apr 9, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 16, 2021 | Aug 17, 2021 | — |
Development fee collection Building Inspection · DFCU | Aug 23, 2021 | Aug 23, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 23, 2021 | Sep 13, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 13, 2021 | Feb 25, 2022 | — |
Addendum 1: Final:foundation, t24, mech, electrical, arch, struc plan
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 28, 2022 | Apr 28, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 28, 2022 | Sep 22, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 28, 2022 | Sep 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2022 | Sep 13, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 30, 2022 | Jul 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2022 | Sep 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 29, 2022 | Sep 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2022 | Nov 23, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $98,000
| Name | Role | License on permit |
|---|---|---|
| Val Larry Dizitser Western Design Co | Architect | C55483 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026