53 V Colton St
San Francisco permit 201911127017 · Mission
To erect 6 stories, 1 basement, type iii-a over i-a, 96 units residential with office, & assembly building. (r-2,b,a-3,s-2) (mayor exective dir# 13-01 & 17-02)
- Filed
- Nov 12, 2019
- Issued
- May 18, 2020 (6 months after filing)
- Completed
- Oct 5, 2022 (29 months after issuance)
- Review stops
- 64 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 15 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building plan review Building Inspection · BLDG | Nov 12, 2019 | Apr 27, 2020 | — |
Zoning review Planning · CP-ZOC | Nov 12, 2019 | Jan 16, 2020 | — |
Fire prevention review Fire Department · SFFD | Nov 12, 2019 | May 11, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 27, 2020 | Apr 28, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2020 | May 7, 2020 | — |
Development fee collection Building Inspection · DFCU | May 8, 2020 | May 8, 2020 | — |
Zoning review Planning · CP-ZOC | May 12, 2020 | May 13, 2020 | — |
Central Permit Bureau Building Inspection · CPB | May 15, 2020 | May 15, 2020 | — |
Permit Processing Center Building Inspection · PPC | May 15, 2020 | May 15, 2020 | — |
Central Permit Bureau Building Inspection · CPB | May 15, 2020 | May 18, 2020 | — |
Addendum 1: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 26, 2020 | May 26, 2020 | — |
Building plan review Building Inspection · BLDG | May 28, 2020 | Oct 3, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jul 16, 2020 | Oct 14, 2020 | — |
Permit Processing Center Building Inspection · PPC | Oct 15, 2020 | Oct 15, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2020 | Oct 15, 2020 | — |
Addendum 2: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 26, 2020 | May 26, 2020 | — |
Building plan review Building Inspection · BLDG | May 28, 2020 | Oct 3, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jul 16, 2020 | Oct 14, 2020 | — |
Permit Processing Center Building Inspection · PPC | Oct 15, 2020 | Oct 15, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2020 | Oct 15, 2020 | — |
Addendum 3: Architectural and mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 21, 2020 | Sep 21, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 21, 2020 | Mar 11, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2020 | Mar 11, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 21, 2020 | Mar 11, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2020 | Feb 23, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2020 | Sep 25, 2020 | — |
Zoning review Planning · CP-ZOC | Sep 21, 2020 | Sep 28, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 21, 2020 | Mar 12, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Oct 30, 2020 | Mar 11, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2021 | Mar 12, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2021 | Mar 12, 2021 | — |
Zoning review Planning · CP-ZOC | Mar 11, 2021 | Mar 12, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Mar 12, 2021 | Mar 12, 2021 | — |
Addendum 4: Fire protection sprinkler
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 3, 2020 | Nov 3, 2020 | — |
Permit Processing Center Building Inspection · PPC | Nov 3, 2020 | May 10, 2021 | — |
Fire prevention review Fire Department · SFFD | Nov 5, 2020 | May 7, 2021 | — |
Central Permit Bureau Building Inspection · CPB | May 10, 2021 | May 12, 2021 | — |
Addendum 5: Fire alarm + 2way ecs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 13, 2021 | Sep 13, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 13, 2021 | Oct 18, 2021 | — |
Permit Processing Center Building Inspection · PPC | Sep 13, 2021 | Oct 22, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 22, 2021 | Oct 22, 2021 | — |
Addendum 6: Steel stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 2, 2021 | Aug 2, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 2, 2021 | Aug 9, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 2, 2021 | Aug 17, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 2, 2021 | Aug 19, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2021 | Aug 24, 2021 | — |
Addendum 7: Window washing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 29, 2021 | Sep 29, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 29, 2021 | Oct 7, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 29, 2021 | Oct 12, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 29, 2021 | Sep 29, 2021 | — |
Permit Processing Center Building Inspection · PPC | Sep 29, 2021 | Oct 13, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 13, 2021 | Oct 13, 2021 | — |
Addendum 8: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 16, 2021 | Jul 19, 2021 | — |
Fire prevention review Fire Department · SFFD | Jul 19, 2021 | Aug 26, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jul 19, 2021 | Sep 1, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 1, 2021 | Sep 2, 2021 | — |
Addendum 9: Exterior glazing storefront system (add)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 23, 2021 | Aug 23, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 23, 2021 | Sep 1, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 23, 2021 | Sep 30, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 31, 2021 | Sep 30, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 31, 2021 | Sep 29, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 31, 2021 | Sep 10, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 31, 2021 | Sep 29, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 30, 2021 | Oct 1, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $25,000,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Elias Simons David Baker Architects | Architect | C30025 |
| Randall James Girouard Access System & Solutions Inc | Engineer | S-5357 |
| Carl Milsum | Engineer | S6190 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025