445 Duncan St
San Francisco permit 201911147292 · Noe Valley
Demolish existing rear sunroom on 2/fl and rebuild & expand aprox 8' new 1 story ground floor. addition approx 8' at rear with deck above and stairs on 2/fl. proposed addition not visible from street.
- Filed
- Nov 14, 2019
- Issued
- Feb 5, 2021 (15 months after filing)
- Completed
- Nov 6, 2023 (33 months after issuance)
- Review stops
- 22 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 14, 2019 | Nov 14, 2019 | — |
Zoning review Planning · CP-ZOC | Nov 14, 2019 | Sep 8, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Apr 29, 2020 | Sep 8, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 2, 2020 | Sep 4, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 10, 2020 | Dec 1, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2020 | Dec 17, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 16, 2020 | Dec 17, 2020 | — |
Zoning review Planning · CP-ZOC | Dec 18, 2020 | Dec 29, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 30, 2020 | Dec 30, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2020 | Feb 5, 2021 | — |
Addendum 1: Grading, foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 24, 2021 | Feb 24, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 10, 2021 | May 20, 2021 | — |
Street use and mapping Public Works · DPW-BSM | May 21, 2021 | Jun 1, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 2, 2021 | Jun 2, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2021 | Jun 25, 2021 | — |
Addendum 2: Final architechural plans, t-24 energy, mech, electrical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 24, 2021 | Feb 24, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 10, 2021 | Jul 27, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | May 27, 2021 | Jun 17, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2021 | Jun 24, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2021 | Jun 30, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jul 29, 2021 | Jul 29, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jul 29, 2021 | Aug 18, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Lisa Ann Harvey Harvey Architecture | Architect | C23004 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2014