600 Indiana St #0
San Francisco permit 201911207807 · Potrero Hill
Change of use from storage to cannabis retail. interior & (e) tenant improvement w/ structural. includes (n) stairs & mezzanine. (n) partition walls & ceiling finishes, lighting, electrical, hvac & plumbing. includes demolitions of windows. exterior door & finishes & (n) storefront installation
- Filed
- Nov 20, 2019
- Issued
- Feb 25, 2022 (27 months after filing)
- Completed
- Not completed yet
- Review stops
- 29 stops across 6 departments
- Comments issued
- 3 times, by Building Inspection, Public Health
- Put on hold
- 9 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 22, 2019 | Nov 22, 2019 | — |
Zoning review Planning · CP-ZOC | Nov 25, 2019 | Aug 25, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Jan 23, 2020 | Aug 25, 2020 | — |
Planning discretionary review Planning · CP-DR | Mar 11, 2020 | Aug 25, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jul 31, 2020 | Nov 12, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 26, 2020 | Sep 30, 2020 | — |
Fire prevention review Fire Department · SFFD | Oct 1, 2020 | Oct 8, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Oct 8, 2020 | Feb 17, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 19, 2020 | Oct 19, 2020 | — |
Public health review Public Health · HEALTH | Oct 20, 2020 | Oct 22, 2020 | — |
Development fee collection Building Inspection · DFCU | Feb 18, 2022 | Feb 18, 2022 | — |
Permit Processing Center Building Inspection · PPC | Feb 18, 2022 | Feb 18, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 18, 2022 | Feb 25, 2022 | — |
Addendum 1: Architectural,structural,t24,elec,mech,plumbing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 9, 2022 | Mar 9, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2022 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Mar 15, 2022 | Jun 29, 2022 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 4, 2022 | Jan 21, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jun 9, 2022 | In progress | — |
Fire prevention review Fire Department · SFFD | Aug 9, 2022 | Aug 18, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2022 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2022 | Aug 24, 2022 | — |
Public health review Public Health · HEALTH | Aug 24, 2022 | Apr 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 21, 2025 | Jan 21, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Public health review Public Health · HEALTH | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $503,370
| Name | Role | License on permit |
|---|---|---|
| Sharon Cox Plinth Architecture | Authorized agent-others | C26342 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026