919 Illinois St
San Francisco permit 201911258098 · Potrero Hill
Mou proj-19-0285 priority processing.to erect a 6-story, type 1b, 1-basement mixed use building w/ 241 residential units, ground level lobby, retail and commercial space. (port site permit b-2019-0321)
- Filed
- Nov 25, 2019
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 40 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 12 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 7, 2020 | Jan 7, 2020 | — |
Zoning review Planning · CP-ZOC | Jan 7, 2020 | Mar 26, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 7, 2020 | Feb 7, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 7, 2020 | Nov 23, 2020 | — |
Fire Department SFFD-PRT | Mar 23, 2020 | Jan 14, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 24, 2020 | Dec 23, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 10, 2020 | Jan 26, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 26, 2021 | Jan 28, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 28, 2021 | Feb 2, 2021 | — |
Fire Department SFFD-PRT | Feb 3, 2021 | Feb 11, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 12, 2021 | Feb 18, 2021 | — |
Development fee collection Building Inspection · DFCU | Feb 19, 2021 | Feb 19, 2021 | — |
Permit Processing Center Building Inspection · PPC | Feb 23, 2021 | Apr 6, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2021 | Feb 25, 2021 | — |
Addendum 1: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 28, 2021 | Nov 18, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2021 | Jan 6, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2021 | Oct 12, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2021 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 18, 2021 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 2: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 28, 2021 | Nov 18, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2021 | Jan 6, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2021 | Aug 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2021 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 18, 2021 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Architectural/mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 28, 2021 | Nov 18, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2021 | Oct 28, 2022 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2021 | In progress | — |
Electrical plan review Building Inspection · MECH-E | Nov 18, 2021 | In progress | — |
Fire Department SFFD-PRT | Nov 18, 2021 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2021 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2021 | Nov 29, 2021 | — |
Plumbing plan check Building Inspection · PID-PC | Nov 18, 2021 | Nov 29, 2021 | Approved |
Zoning review Planning · CP-ZOC | Nov 18, 2021 | Jan 21, 2022 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 18, 2021 | In progress | — |
Zoning review Planning · CP-ZOC | Sep 20, 2022 | Oct 12, 2023 | Administrative |
Building plan review Building Inspection · BLDG | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Approved
- Estimated cost
- $150,000,000
| Name | Role | License on permit |
|---|---|---|
| Glenn G Rescalvo Handel Architects,Llp | Architect | C-27080 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026