1950 Jackson St
San Francisco permit 201912098990 · Pacific Heights
Temporary change of use to consulate and visa office. seismic, security, mep, & sprinkler upgrades. programatic modifications. building to return to residenical use during later phase. raising portion of brick wall.
- Filed
- Dec 9, 2019
- Issued
- Jan 3, 2023 (37 months after filing)
- Completed
- Not completed yet
- Review stops
- 33 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 8 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 17, 2019 | Dec 17, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 17, 2019 | Feb 1, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Aug 6, 2020 | Sep 1, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Oct 5, 2020 | Oct 5, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 29, 2021 | May 9, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 29, 2021 | Feb 16, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 29, 2021 | Mar 12, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2021 | Jul 15, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jan 29, 2021 | Dec 20, 2022 | — |
Building plan review Building Inspection · BLDG | May 9, 2022 | Nov 1, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 28, 2022 | Dec 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2022 | Dec 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2022 | Nov 4, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 19, 2022 | Dec 19, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2022 | Jan 3, 2023 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 12, 2023 | Jan 12, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 13, 2023 | Jun 21, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 13, 2023 | Aug 3, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2023 | Jul 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2023 | Jun 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 13, 2023 | Jan 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2023 | Jan 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 13, 2023 | Aug 11, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 13, 2023 | Jul 20, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 13, 2023 | Mar 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2023 | Jun 28, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2023 | Jul 12, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jul 12, 2023 | Jul 12, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2023 | Jul 20, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2023 | Jul 21, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Aug 2, 2023 | Aug 2, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 4, 2023 | Aug 7, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2023 | Sep 19, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $6,000,000
| Name | Role | License on permit |
|---|---|---|
| Nancy Gail Goldenberg Treanorhl | Architect | C25019 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025