1960 Jackson St
San Francisco permit 201912098993 · Pacific Heights
Seismic upgrade. security upgrades. mep including new wiring, accessiblility, sprinklers, programmatic modifications. removal of a portion of front wall for guard house, raising of a portion of the brick wall for security. ** maher: n/a **
- Filed
- Dec 9, 2019
- Issued
- Jan 3, 2023 (37 months after filing)
- Completed
- Not completed yet
- Review stops
- 32 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Fire prevention review Fire Department · SFFD | Dec 11, 2019 | Dec 11, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Dec 17, 2019 | Dec 17, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 17, 2019 | Jan 13, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 5, 2020 | Oct 5, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 13, 2021 | Apr 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2021 | Jan 13, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2021 | Jul 9, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jan 13, 2021 | Dec 20, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 16, 2021 | Feb 16, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 22, 2022 | Nov 1, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 28, 2022 | Dec 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2022 | Dec 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2022 | Nov 4, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 19, 2022 | Dec 19, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2022 | Jan 3, 2023 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 12, 2023 | Jan 12, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 12, 2023 | Aug 3, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2023 | Jun 21, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2023 | Jul 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2023 | Jun 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 13, 2023 | Jan 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2023 | Jan 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 13, 2023 | Aug 11, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 13, 2023 | Jul 20, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 13, 2023 | Mar 17, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2023 | Jun 28, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2023 | Jul 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2023 | Jul 20, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2023 | Jul 21, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Aug 2, 2023 | Aug 2, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 7, 2023 | Aug 7, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2023 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $7,900,000
| Name | Role | License on permit |
|---|---|---|
| Nancy Gail Goldenberg Treanorhl | Architect | C25019 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026