1360 43rd Av
San Francisco permit 201912099009 · Sunset/Parkside
Priority project, mayor ed 13-01. to erect a type 3a over type 1a, 5-story, 100% afforable educator building w/ 135 residential units.
- Filed
- Dec 9, 2019
- Issued
- Jan 11, 2021 (13 months after filing)
- Completed
- Mar 5, 2025 (50 months after issuance)
- Review stops
- 141 stops across 7 departments
- Comments issued
- 10 times, by Fire Department, Building Inspection, Permit Center
- Put on hold
- 34 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 9, 2019 | Dec 9, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 9, 2019 | May 22, 2020 | — |
Building plan review Building Inspection · BLDG | Dec 9, 2019 | Jan 30, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 29, 2020 | Oct 13, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2020 | Feb 26, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2020 | Oct 13, 2020 | — |
Building plan review Building Inspection · BLDG | Apr 16, 2020 | Oct 7, 2020 | — |
Disability access review Mayor's Office on Disability · MOD | Apr 24, 2020 | Oct 13, 2020 | — |
Fire Department housing review Fire Department · SFFD-HQ | May 21, 2020 | Oct 29, 2020 | — |
Building plan review Building Inspection · BLDG | Oct 7, 2020 | Oct 9, 2020 | — |
Development fee collection Building Inspection · DFCU | Dec 3, 2020 | Dec 4, 2020 | — |
Zoning review Planning · CP-ZOC | Dec 4, 2020 | Dec 9, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 4, 2020 | Dec 12, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2020 | Jan 11, 2021 | — |
Addendum 1: Foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 23, 2020 | Jan 11, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 5, 2021 | Nov 1, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Feb 5, 2021 | Jan 5, 2022 | — |
Permit Processing Center Building Inspection · PPC | Feb 5, 2021 | Jan 11, 2022 | — |
Development fee collection Building Inspection · DFCU | Jun 23, 2021 | Jun 23, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jan 11, 2022 | Jun 9, 2022 | — |
Addendum 2: Arch,mep, code/accessibility reqd signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 23, 2020 | Jan 11, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 14, 2021 | Apr 22, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 14, 2021 | Apr 7, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2021 | Mar 16, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jan 14, 2021 | Jan 12, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 14, 2021 | Jan 10, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 14, 2021 | Aug 27, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 14, 2021 | Mar 9, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Jan 14, 2021 | Mar 31, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 14, 2021 | Apr 22, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 19, 2021 | Aug 26, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2021 | Dec 22, 2021 | — |
Urban forestry Public Works · DPW-BUF | Jan 27, 2022 | Feb 7, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 13, 2022 | Apr 18, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 13, 2022 | Apr 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 13, 2022 | Apr 21, 2022 | — |
Urban forestry Public Works · DPW-BUF | Apr 13, 2022 | Apr 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 13, 2022 | Apr 15, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2022 | Jun 9, 2022 | — |
Addendum 3: Shoring,excavation,rough grading
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 8, 2021 | Nov 8, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 8, 2021 | Sep 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 8, 2021 | Aug 29, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 8, 2021 | Sep 15, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jan 27, 2022 | Mar 11, 2022 | — |
Urban forestry Public Works · DPW-BUF | Sep 1, 2022 | Sep 14, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 15, 2022 | Sep 15, 2022 | — |
Addendum 4: Stormwater, civil, landscape
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 20, 2021 | Dec 20, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 20, 2021 | Jul 27, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2021 | Dec 29, 2021 | — |
Plumbing plan check Building Inspection · PID-PC | Dec 20, 2021 | Apr 7, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 20, 2021 | Jul 11, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2021 | Mar 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2021 | Aug 29, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Dec 20, 2021 | Jul 1, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 20, 2021 | Aug 17, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 20, 2021 | Aug 30, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jan 27, 2022 | Feb 7, 2022 | — |
Plumbing plan check Building Inspection · PID-PC | Aug 5, 2022 | Aug 22, 2022 | — |
Urban forestry Public Works · DPW-BUF | Aug 5, 2022 | Aug 12, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Aug 5, 2022 | Aug 16, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 30, 2022 | Aug 31, 2022 | — |
Addendum 5: Fire sprinkler system (design-build)per nfpa 13
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 9, 2022 | Jun 9, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 9, 2022 | Mar 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 9, 2022 | May 10, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 23, 2023 | Apr 27, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 17, 2023 | May 8, 2023 | — |
Fire prevention review Fire Department · SFFD | May 4, 2023 | May 8, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 10, 2023 | May 31, 2023 | — |
Addendum 6: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 14, 2022 | Nov 14, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 14, 2022 | Dec 28, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 15, 2022 | Dec 27, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 28, 2022 | Dec 30, 2022 | — |
Addendum 7: Fire alarm system & 2-way communication
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 23, 2022 | Nov 23, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 23, 2022 | Oct 12, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 23, 2022 | Jan 10, 2024 | In Progress |
Fire prevention review Fire Department · SFFD | Nov 10, 2023 | Dec 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jan 9, 2024 | Jan 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2024 | Jan 12, 2024 | Administrative |
Addendum 8: Shear wall tie down system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 5, 2023 | May 11, 2023 | — |
Building plan review Building Inspection · BLDG | May 11, 2023 | Jul 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 11, 2023 | May 24, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 11, 2023 | Jul 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 6, 2023 | Jul 6, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 11, 2023 | Jul 12, 2023 | — |
Addendum 9: Solar photovoltaic system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 19, 2023 | Jul 19, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jul 20, 2023 | Jul 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 20, 2023 | Aug 1, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 20, 2023 | Aug 24, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 24, 2023 | Aug 29, 2023 | Administrative |
Addendum 10: Metal stairs (design build)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 18, 2023 | May 18, 2023 | — |
Building plan review Building Inspection · BLDG | May 18, 2023 | Jun 22, 2023 | — |
Fire prevention review Fire Department · SFFD | May 18, 2023 | May 24, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 18, 2023 | Jul 3, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 20, 2023 | Jun 27, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 29, 2023 | Jun 30, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 29, 2023 | Jul 3, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2023 | Jul 6, 2023 | — |
Addendum 11: Exterior building maintenance (ebm)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 24, 2023 | Jul 24, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 24, 2023 | Aug 10, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 24, 2023 | Aug 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2023 | Aug 3, 2023 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Jul 24, 2023 | Sep 8, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 8, 2023 | Sep 8, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 8, 2023 | Sep 12, 2023 | Administrative |
Addendum 12: Signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 31, 2024 | Feb 6, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2024 | Mar 20, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 5, 2024 | Feb 5, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 6, 2024 | Feb 6, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Feb 7, 2024 | Feb 7, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 11, 2024 | Mar 19, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 12, 2024 | Mar 12, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 12, 2024 | Mar 12, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 20, 2024 | Jun 10, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 20, 2024 | Mar 27, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Mar 20, 2024 | Mar 28, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 20, 2024 | Mar 22, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 20, 2024 | Jun 26, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | Apr 30, 2024 | Apr 30, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | May 3, 2024 | May 3, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 17, 2024 | May 17, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 20, 2024 | May 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 20, 2024 | May 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 17, 2024 | Jun 26, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 17, 2024 | Jun 24, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Jun 17, 2024 | Jun 20, 2024 | Not Applicable |
Fire prevention review Fire Department · SFFD | Jun 17, 2024 | Jun 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 26, 2024 | Jun 27, 2024 | Administrative |
Addendum 13: Evacuation signs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 20, 2023 | Sep 20, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 20, 2023 | Oct 2, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Sep 20, 2023 | Oct 2, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2023 | Oct 4, 2023 | Administrative |
Addendum 14: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 7, 2023 | Jul 7, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 7, 2023 | Jul 27, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 9, 2023 | Aug 11, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 11, 2023 | Aug 11, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2023 | Aug 14, 2023 | Administrative |
Addendum 15: Steel studs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 13, 2023 | Oct 13, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 13, 2023 | Nov 2, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 13, 2023 | Nov 27, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 20, 2023 | Nov 27, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 27, 2023 | Dec 11, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $40,000,000
| Name | Role | License on permit |
|---|---|---|
| Christian Niel Haegglund Bar Architects | Architect | C18896 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
| David Joseph Rossi Kpff | Engineer | 4127 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025