30 Van Ness Av
San Francisco permit 201912139539 · Tenderloin
(e) walls to remain - (n) high rise bldg w/ appoxi 853,400 gsf/515'-4" tall w/ family/office mixed use type 1 construction. including a grd flr residential lobby, 5000 s.f. retail space, 2 below grade basement parking, 7 levels of office w/ terraces, residences from level 11-47. total 348 units.
- Filed
- Dec 13, 2019
- Issued
- Aug 25, 2021 (20 months after filing)
- Completed
- Not completed yet
- Review stops
- 50 stops across 6 departments
- Comments issued
- Once, by Fire Department
- Put on hold
- 20 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 18, 2019 | Dec 18, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 18, 2019 | Dec 24, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 26, 2019 | Nov 4, 2020 | — |
Fire prevention review Fire Department · SFFD | Apr 8, 2020 | Jan 26, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 14, 2020 | Jul 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 26, 2020 | Sep 8, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2021 | Feb 9, 2021 | — |
Public health review Public Health · HEALTH | Jan 26, 2021 | Jan 28, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 6, 2021 | Aug 19, 2021 | — |
Development fee collection Building Inspection · DFCU | Aug 20, 2021 | Aug 20, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 20, 2021 | Aug 20, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 20, 2021 | Aug 25, 2021 | — |
Addendum 1: Foundation (below grade)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 25, 2021 | Mar 16, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 27, 2021 | Oct 8, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 2, 2021 | Mar 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2021 | Mar 14, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 15, 2023 | Mar 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2023 | Mar 16, 2023 | — |
Addendum 2: Superstructure.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 25, 2021 | Aug 26, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 27, 2021 | Oct 8, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 2, 2021 | Mar 14, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2021 | Mar 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Nov 22, 2021 | Nov 23, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 15, 2023 | Mar 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2023 | Mar 16, 2023 | — |
Addendum 3: Architectural, mep & landscape.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 25, 2021 | Aug 26, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 27, 2021 | Jul 13, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 27, 2021 | Jul 18, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 27, 2021 | Aug 26, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Sep 3, 2021 | Jul 26, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 10, 2021 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 17, 2021 | Sep 7, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 6, 2022 | In progress | — |
Fire prevention review Fire Department · SFFD | Apr 3, 2023 | Apr 7, 2023 | — |
Plumbing plan check Building Inspection · PID-PC | Apr 26, 2023 | Apr 27, 2023 | — |
Plumbing plan check Building Inspection · PID-PC | May 11, 2023 | May 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 21, 2023 | Jul 24, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 26, 2023 | Jul 28, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 5: Fire protection.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 14, 2023 | Mar 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 14, 2023 | Jun 5, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 14, 2023 | Jun 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 7, 2023 | Jun 13, 2023 | — |
Addendum 7: Steel stairs.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 17, 2023 | Mar 28, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 28, 2023 | May 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 28, 2023 | Sep 7, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 28, 2023 | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $244,000,000
| Name | Role | License on permit |
|---|---|---|
| Peter J Noone Solomon Cordwell Buenz | Architect | C31296 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026