127 Collingwood St #0
San Francisco permit 201912189884 · Castro/Upper Market
Enclosing (e) driveway area as ground flr reception and hallway. converting unused garage into program space with accessible route through rear yard.
- Filed
- Dec 18, 2019
- Issued
- Feb 23, 2022 (26 months after filing)
- Completed
- Not completed yet
- Review stops
- 39 stops across 6 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 18, 2019 | Dec 18, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 18, 2019 | Feb 1, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 3, 2021 | Oct 4, 2021 | — |
Disability access review Mayor's Office on Disability · MOD | Mar 10, 2021 | Sep 27, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 1, 2021 | Nov 5, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 8, 2021 | Jun 9, 2021 | — |
Disability access review Mayor's Office on Disability · MOD | Aug 3, 2021 | Sep 27, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 8, 2021 | Oct 13, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 8, 2021 | Oct 27, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 8, 2021 | Feb 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 8, 2021 | Nov 12, 2021 | — |
Fire prevention review Fire Department · SFFD | Dec 22, 2021 | Dec 22, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 28, 2022 | Feb 1, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 28, 2022 | Feb 2, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 1, 2022 | Feb 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2022 | Feb 23, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 11, 2022 | Feb 11, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 14, 2022 | Feb 14, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 15, 2022 | Feb 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 15, 2022 | Feb 15, 2022 | — |
Addendum 1: Struct, arch, t24, final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 27, 2022 | Oct 27, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 28, 2022 | Jan 17, 2023 | Administrative |
Disability access review Mayor's Office on Disability · MOD | Dec 14, 2022 | Jun 30, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 17, 2023 | Mar 21, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2023 | Sep 22, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 10, 2023 | Oct 11, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 10, 2023 | May 15, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 15, 2023 | May 16, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 5, 2023 | Jul 5, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 24, 2023 | Aug 24, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 24, 2023 | Aug 24, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2023 | Sep 1, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Oct 27, 2023 | Nov 2, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2023 | Nov 7, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 7, 2023 | Nov 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2023 | Nov 16, 2023 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Nov 17, 2023 | Nov 17, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 20, 2023 | Nov 20, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 20, 2023 | Jan 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Chadwick Hamilton Hamilton + Aitken Architects | Architect | C15932 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025