921 Howard St
San Francisco permit 201912230270 · South of Market
Erect 17-story, type 1, 203 dwelling units, residential/commercial building. new bldg will be on block 3732, lots 004, 099, 100, 145a, & 146. 100% affordable housing development by tenderloin neighborhood development corp(tndc). fee defer till 1st addendum issue. comply maher ord.
- Filed
- Dec 23, 2019
- Issued
- May 24, 2021 (17 months after filing)
- Completed
- Oct 17, 2023 (29 months after issuance)
- Review stops
- 114 stops across 7 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 22 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 23, 2019 | Dec 23, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 23, 2019 | Aug 13, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 11, 2020 | Dec 21, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 12, 2020 | Dec 15, 2020 | — |
Fire prevention review Fire Department · SFFD | Aug 12, 2020 | Dec 14, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2020 | Oct 27, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2020 | Oct 21, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Aug 17, 2020 | Dec 21, 2020 | — |
Development fee collection Building Inspection · DFCU | Nov 23, 2020 | Nov 23, 2020 | — |
Zoning review Planning · CP-ZOC | Dec 15, 2020 | Dec 15, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2020 | Dec 18, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2020 | Dec 18, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Dec 21, 2020 | Dec 22, 2020 | — |
Addendum 1: Foundation/superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2020 | Dec 23, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 23, 2020 | Apr 22, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 29, 2020 | Jan 5, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 29, 2020 | Feb 3, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 5, 2021 | Apr 20, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Apr 21, 2021 | Apr 22, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2021 | May 24, 2021 | — |
Addendum 2: Architectural/mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 24, 2021 | Feb 24, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 24, 2021 | Feb 24, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2021 | Feb 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 24, 2021 | Feb 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2021 | Jul 16, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2021 | Mar 12, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 24, 2021 | Nov 8, 2021 | — |
Permit Processing Center Building Inspection · PPC | Feb 24, 2021 | Mar 18, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Feb 26, 2021 | Feb 28, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | May 19, 2021 | Jan 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 13, 2021 | Feb 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2021 | Oct 19, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2021 | Oct 21, 2021 | — |
Disability access review Mayor's Office on Disability · MOD | Mar 2, 2022 | Mar 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 2, 2022 | Mar 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2022 | Mar 7, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 2, 2022 | Mar 9, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2022 | Mar 18, 2022 | — |
Addendum 3: Piles & shoring
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 3, 2021 | May 21, 2021 | — |
Building plan review Building Inspection · BLDG | May 21, 2021 | Jun 22, 2021 | — |
Permit Processing Center Building Inspection · PPC | May 21, 2021 | Jun 30, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 30, 2021 | Jun 30, 2021 | — |
Addendum 4: Stormwater
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 4, 2022 | Mar 4, 2022 | — |
Plumbing plan check Building Inspection · PID-PC | Mar 4, 2022 | Mar 8, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 4, 2022 | Mar 24, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 24, 2022 | Mar 25, 2022 | — |
Addendum 5: Exterior skin precast
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 20, 2021 | Sep 7, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 7, 2021 | Nov 10, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 7, 2021 | Oct 6, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Sep 7, 2021 | Sep 7, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 7, 2021 | Oct 20, 2021 | — |
Permit Processing Center Building Inspection · PPC | Sep 7, 2021 | Nov 18, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2021 | Nov 18, 2021 | — |
Addendum 6: Exterior skin glazing/storefront
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2022 | Oct 26, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 26, 2022 | Dec 20, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 26, 2022 | Nov 30, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 26, 2022 | Dec 17, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 26, 2022 | Dec 30, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2022 | Jan 3, 2023 | — |
Addendum 7: Metal stairs - 1 & 2
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 18, 2021 | Nov 18, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2021 | Dec 10, 2021 | — |
Fire prevention review Fire Department · SFFD | Nov 18, 2021 | Dec 16, 2021 | — |
Permit Processing Center Building Inspection · PPC | Nov 18, 2021 | Apr 12, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Dec 7, 2021 | Apr 6, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 11, 2022 | Apr 12, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 11, 2022 | Apr 11, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2022 | Apr 12, 2022 | — |
Addendum 8: Exterior stairs - 3 & 4
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 6, 2022 | Apr 6, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 6, 2022 | Apr 12, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 6, 2022 | Apr 14, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 6, 2022 | May 24, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 24, 2022 | May 24, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | — | May 10, 2022 | — |
Addendum 9: Fire sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2022 | Mar 10, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 10, 2022 | Jun 6, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 10, 2022 | Jun 13, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2022 | Jun 13, 2022 | — |
Addendum 10: Fire alarm system, elevator landing & two way comm sys
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 2, 2022 | Dec 2, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 2, 2022 | Apr 4, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 2, 2022 | Apr 6, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 6, 2023 | Apr 6, 2023 | — |
Addendum 11: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 17, 2022 | Feb 17, 2022 | — |
Permit Processing Center Building Inspection · PPC | Feb 17, 2022 | Mar 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 18, 2022 | Mar 10, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 15, 2022 | Mar 16, 2022 | — |
Addendum 12: Generator, fuel oil, and piping
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 10, 2022 | May 10, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 10, 2022 | Feb 27, 2023 | — |
Building plan review Building Inspection · BLDG | May 11, 2022 | Jan 24, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 11, 2022 | Nov 9, 2022 | — |
Fire Department housing review Fire Department · SFFD-HQ | May 11, 2022 | Feb 27, 2023 | — |
Electrical plan review Building Inspection · MECH-E | May 23, 2022 | Nov 2, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 2, 2022 | Nov 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2022 | Jan 24, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jan 23, 2023 | Jan 24, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 16, 2023 | Feb 16, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 16, 2023 | Feb 23, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 16, 2023 | Feb 21, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2023 | Mar 1, 2023 | — |
Addendum 13: Exterior building maintenance
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 9, 2021 | Dec 9, 2021 | — |
Permit Processing Center Building Inspection · PPC | Dec 9, 2021 | Jan 4, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 10, 2021 | Jan 3, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 10, 2021 | Dec 16, 2021 | — |
Fire prevention review Fire Department · SFFD | Dec 10, 2021 | Dec 14, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jan 4, 2022 | Jan 4, 2022 | — |
Addendum 14: Evacuation signage (withdrawn)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 30, 2023 | Jan 30, 2023 | — |
Addendum 15: Fsae
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 12, 2023 | Apr 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 13, 2023 | Apr 25, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 13, 2023 | Apr 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 27, 2023 | Apr 27, 2023 | — |
Addendum 16: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 18, 2023 | Jan 18, 2023 | — |
Public health review Public Health · HEALTH | Jan 18, 2023 | Jan 20, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 18, 2023 | Jan 23, 2023 | — |
Public Health HEALTH-HM | Jan 19, 2023 | Jan 20, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2023 | Jan 26, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $70,000,000
| Name | Role | License on permit |
|---|---|---|
| Steven Perry Pier28 | Architect | C26289 |
| Kai Shing Chu Spi Consulting Engineers, Inc. | Engineer | C84827 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025