1240 Fillmore St
San Francisco permit 201912270828 · Western Addition
Conversion of(8) ada units, selective seismic strengthening, replacement of exterior windows, selected roof replacement,(n)residence activity space @ (e) bldg envelope, finishes upgrade @ lobby, office, common community spaces & restrom upgrades, fire sprinkler upgrade, generator replacement.
- Filed
- Dec 27, 2019
- Issued
- Jun 16, 2021 (18 months after filing)
- Completed
- May 3, 2024 (35 months after issuance)
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 30, 2019 | Dec 30, 2019 | — |
Building plan review Building Inspection · BLDG | Dec 31, 2019 | Mar 3, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 2, 2020 | Mar 3, 2020 | — |
Zoning review Planning · CP-ZOC | Mar 3, 2020 | Sep 24, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 24, 2020 | May 21, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 8, 2021 | May 27, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 12, 2021 | May 28, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Mar 1, 2021 | May 28, 2021 | — |
Fire prevention review Fire Department · SFFD | Mar 1, 2021 | Jun 3, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 15, 2021 | Jun 7, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2021 | Apr 6, 2021 | — |
Zoning review Planning · CP-ZOC | May 19, 2021 | May 20, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2021 | May 25, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 7, 2021 | Jun 10, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2021 | Jun 16, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $15,000,000
| Name | Role | License on permit |
|---|---|---|
| Daniel M Levine The John Stewart Company | Architect | C10154 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026