4006 25th St
San Francisco permit 201912311084 · Noe Valley
Rear horizontal additon @ basement & 1st floor kitchen.(n) coat closert & powder rm. in(e) dining room.(n)master bath on part of (e) 2nd floor open deck replace (e) gas gravity furnace & dosmestic hot water with heat pump. new adu @ 1st floor.
- Filed
- Dec 31, 2019
- Issued
- Nov 12, 2024 (58 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 4 departments
- Comments issued
- None
- Put on hold
- 7 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 31, 2019 | Dec 31, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 31, 2019 | Dec 10, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Jun 18, 2020 | Dec 4, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2020 | Dec 1, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 1, 2020 | Jun 13, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 10, 2020 | Feb 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 10, 2020 | Jan 11, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 10, 2020 | Apr 26, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 10, 2020 | Jul 8, 2021 | — |
Zoning review Planning · CP-ZOC | Mar 15, 2022 | May 3, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 15, 2022 | Jan 4, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 15, 2022 | Mar 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2022 | Mar 17, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 5, 2022 | Oct 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2022 | Oct 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 3, 2023 | Mar 30, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 3, 2023 | Jan 5, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 17, 2023 | Feb 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 17, 2023 | Feb 21, 2023 | — |
Development fee collection Building Inspection · DFCU | May 4, 2023 | May 4, 2023 | — |
Zoning review Planning · CP-ZOC | May 5, 2023 | May 17, 2023 | — |
Building plan review Building Inspection · BLDG | May 5, 2023 | May 5, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2023 | May 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2023 | May 10, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 5, 2023 | Jun 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2023 | Nov 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Frederic Harris Knapp Knapp Architects | Payor | C23056 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022