4227 24th St
San Francisco permit 201912311126 · Noe Valley
Interior & exterior alterations include adding one story to the (e) 2 story home,expanding of all floors toward rear property line, news and doors, three additional bathrooms, all new electrical, plumbing & heating systems upgraded structural work. no change to use or occupancy.
- Filed
- Dec 31, 2019
- Issued
- Apr 1, 2021 (15 months after filing)
- Completed
- Jun 5, 2023 (26 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 31, 2019 | Dec 31, 2019 | — |
Zoning review Planning · CP-ZOC | Jan 2, 2020 | Oct 9, 2020 | — |
Planning neighborhood notice Planning · CP-NP | Aug 3, 2020 | Sep 14, 2020 | — |
Building plan review Building Inspection · BLDG | Oct 13, 2020 | Jan 9, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 30, 2020 | Feb 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 14, 2020 | Jan 4, 2021 | — |
Development fee collection Building Inspection · DFCU | Feb 1, 2021 | Feb 1, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2021 | Feb 24, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 24, 2021 | Mar 15, 2021 | — |
Permit Processing Center Building Inspection · PPC | Mar 16, 2021 | Mar 16, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2021 | Apr 1, 2021 | — |
Addendum 1: Final architectural, structural, mechanical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 14, 2021 | Apr 14, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 15, 2021 | Aug 5, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2021 | Aug 11, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2021 | Aug 18, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2021 | Jul 28, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 19, 2021 | Aug 19, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2021 | Aug 27, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $800,000
| Name | Role | License on permit |
|---|---|---|
| Kristen Johnson Haller Haller Architecture & Design | Architect | C32724 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026