2506 28th Av
San Francisco permit 202001272826 · Sunset/Parkside
Add adu per ord# 95-17. convert the 1st floor to a 2 bedroom, 1 bathroom and 1 kitchen/dining room. lower the floor to gain the required ceiling height.
- Filed
- Jan 27, 2020
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 13 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 27, 2020 | Jan 27, 2020 | — |
Intake Building Inspection · INTAKE | Feb 14, 2020 | Feb 14, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2020 | Feb 27, 2020 | — |
Zoning review Planning · CP-ZOC | Feb 27, 2020 | In progress | — |
Building plan review Building Inspection · BLDG | Mar 24, 2020 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 31, 2020 | Mar 31, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 1, 2020 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Apr 20, 2020 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Apr 24, 2020 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Apr 30, 2020 | May 13, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 30, 2020 | Jun 25, 2020 | — |
Permit Processing Center Building Inspection · PPC | Nov 10, 2020 | Nov 10, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Nov 10, 2020 | Nov 17, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Withdrawn
- Estimated cost
- $80,000
| Name | Role | License on permit |
|---|---|---|
| Senthilnath Puliyadi Zenith Engineers | Engineer | C71630 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022