474 Valley St
San Francisco permit 202001313281 · Noe Valley
Vertical & horizontal addition. 1st floor: entry, garage, 2 bedroom, 2 bath, laundry. 2nd floor: great room, 1 bedroom, 1 bath, one 1/2 bath. 3rd floor: great room, 1 bedroom, 1 bath, one 1/2 bath, laundry. 4th floor: 2 bedrooms, 2 baths. install sprinkler system @ all levels under seperate permit.
- Filed
- Jan 31, 2020
- Issued
- Feb 7, 2022 (24 months after filing)
- Completed
- Not completed yet
- Review stops
- 25 stops across 5 departments
- Comments issued
- None
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 31, 2020 | Jan 31, 2020 | — |
Zoning review Planning · CP-ZOC | Jan 31, 2020 | May 26, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Apr 6, 2021 | Apr 12, 2021 | — |
Building plan review Building Inspection · BLDG | May 27, 2021 | Jan 4, 2022 | — |
Building plan review Building Inspection · BLDG | May 27, 2021 | Jul 7, 2021 | — |
Fire prevention review Fire Department · SFFD | Jul 15, 2021 | Jan 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2021 | Aug 27, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 30, 2021 | Sep 22, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 4, 2022 | Jan 4, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 4, 2022 | Jan 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 7, 2022 | Jan 10, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 11, 2022 | Jan 24, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 25, 2022 | Jan 27, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 28, 2022 | Jan 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2022 | Feb 4, 2022 | — |
Addendum 1: Arch/structural/t24/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 9, 2022 | Feb 9, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 10, 2022 | May 31, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2022 | May 27, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 19, 2022 | May 31, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 27, 2022 | Aug 4, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jun 6, 2022 | Jul 18, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 22, 2022 | Jun 24, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 8, 2022 | Aug 12, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 12, 2022 | Sep 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 6, 2022 | Nov 1, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $878,907
| Name | Role | License on permit |
|---|---|---|
| William Keith Egan Bill Egan Architect | Architect | C9719 |
| Donald David Double D Engineering | Engineer | S-3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025