561 Duncan St
San Francisco permit 202002285791 · Noe Valley
Interior remodel and rear horizontal & vertical expansion, add a new dwelling unit.
- Filed
- Feb 28, 2020
- Issued
- Nov 3, 2021 (20 months after filing)
- Completed
- Nov 12, 2025 (48 months after issuance)
- Review stops
- 26 stops across 4 departments
- Comments issued
- Once, by Public Works
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 2, 2020 | Mar 2, 2020 | — |
Zoning review Planning · CP-ZOC | Mar 2, 2020 | May 26, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 30, 2021 | Apr 1, 2021 | — |
Building plan review Building Inspection · BLDG | May 27, 2021 | Sep 17, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 4, 2021 | Aug 11, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2021 | Sep 9, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 20, 2021 | Sep 21, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2021 | Sep 27, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2021 | Sep 29, 2021 | — |
Development fee collection Building Inspection · DFCU | Oct 1, 2021 | Oct 1, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 1, 2021 | Oct 1, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Oct 1, 2021 | Nov 3, 2021 | — |
Addendum 1: Arch, structural, title 24, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 24, 2022 | Mar 24, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 24, 2022 | Jul 29, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 1, 2022 | Jan 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 13, 2022 | Apr 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 16, 2022 | May 8, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2022 | Nov 28, 2022 | — |
Urban forestry Public Works · DPW-BUF | Apr 1, 2024 | Apr 1, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 11, 2024 | Apr 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 19, 2024 | Apr 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 22, 2024 | Apr 29, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 29, 2024 | May 2, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 6, 2024 | May 10, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 10, 2024 | May 28, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | May 14, 2024 | May 14, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $750,000
| Name | Role | License on permit |
|---|---|---|
| Jennifer Ann Butler | Payor | C38101 |
| Richard A Merlau | Architect | C38697 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025