271 Minerva St
San Francisco permit 202003126918 · Oceanview/Merced/Ingleside
Horizontal addition to current levels: add a bedroom, bathroom and wet bar at level 1, enlarge kitchen and living/dining, relocate 2 bedrooms into 1 bedroom with new bath and 1 office, reloc bath all at level 2. 2 new decks at rear.
- Filed
- Mar 12, 2020
- Issued
- Nov 1, 2023 (44 months after filing)
- Completed
- Not completed yet
- Review stops
- 42 stops across 6 departments
- Comments issued
- 7 times, by Fire Department, Permit Center, Building Inspection, Public Works
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 15, 2020 | Aug 26, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 26, 2020 | Oct 2, 2023 | Administrative |
Planning pre-screening Planning · PRE-PLN | Aug 28, 2020 | Oct 6, 2020 | — |
Building pre-screening Building Inspection · PRE-BLDG | Aug 28, 2020 | Sep 8, 2020 | — |
Zoning review Planning · CP-ZOC | Oct 7, 2020 | Dec 2, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Oct 3, 2022 | Dec 2, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 2, 2022 | May 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2022 | Dec 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2022 | Dec 16, 2022 | — |
Urban forestry Public Works · DPW-BUF | Dec 9, 2022 | May 24, 2023 | Approved |
Zoning review Planning · CP-ZOC | May 3, 2023 | Jun 21, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 3, 2023 | Sep 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 3, 2023 | May 4, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 27, 2023 | Jul 3, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 27, 2023 | Jun 30, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 27, 2023 | Jun 27, 2023 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Jul 3, 2023 | Jul 27, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 22, 2023 | Sep 29, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2023 | Nov 1, 2023 | Administrative |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 19, 2024 | Feb 26, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 23, 2024 | Feb 23, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2024 | Mar 14, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Feb 26, 2024 | Feb 26, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 26, 2024 | Feb 26, 2024 | Not Applicable |
Permit Center Permit Center · PERMIT-CTR | Feb 26, 2024 | Mar 6, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Mar 5, 2024 | Mar 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 14, 2024 | May 7, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 14, 2024 | Apr 19, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 14, 2024 | Aug 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2024 | Mar 19, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2024 | Mar 21, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 14, 2024 | Sep 17, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Mar 22, 2024 | Apr 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2024 | Apr 10, 2024 | Approved |
Mechanical plan review quality control Building Inspection · MECH-QC | Apr 19, 2024 | Apr 19, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | May 3, 2024 | Sep 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2024 | Aug 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 19, 2024 | Aug 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 19, 2024 | Aug 21, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2024 | Aug 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2024 | Aug 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2024 | Apr 17, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $416,925
| Name | Role | License on permit |
|---|---|---|
| Young Woo Son Young Woo | Architect | C37446 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025