180 Jones St
San Francisco permit 202004307276 · Tenderloin
To erect a type-1b, 9-story, 70-dwelling unit bldg with zero basements.
- Filed
- Apr 30, 2020
- Issued
- Sep 11, 2020 (4 months after filing)
- Completed
- Sep 3, 2024 (48 months after issuance)
- Review stops
- 84 stops across 7 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 23 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Zoning review Planning · CP-ZOC | Mar 23, 2020 | Aug 19, 2020 | — |
Building plan review Building Inspection · BLDG | Apr 21, 2020 | Aug 19, 2020 | — |
Disability access review Mayor's Office on Disability · MOD | May 7, 2020 | Aug 31, 2020 | — |
Street use and mapping Public Works · DPW-BSM | May 11, 2020 | Aug 26, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2020 | Aug 31, 2020 | — |
Fire prevention review Fire Department · SFFD | May 26, 2020 | Aug 19, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2020 | Sep 10, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 10, 2020 | Sep 10, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2020 | Sep 11, 2020 | — |
Addendum 1: Foundation and superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 10, 2020 | Nov 18, 2020 | — |
Permit Processing Center Building Inspection · PPC | Nov 18, 2020 | May 2, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 2, 2020 | Jan 21, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2020 | Apr 26, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Dec 15, 2020 | Feb 18, 2022 | — |
Public health review Public Health · HEALTH | Feb 16, 2021 | May 13, 2021 | — |
Central Permit Bureau Building Inspection · CPB | May 2, 2022 | May 31, 2022 | — |
Addendum 2: Architecture, landscape architecture, mep and low voltage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2020 | Dec 22, 2020 | — |
Permit Processing Center Building Inspection · PPC | Dec 22, 2020 | Aug 2, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 13, 2021 | Jul 20, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2021 | Jun 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 13, 2021 | Jul 21, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2021 | Jul 19, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2021 | Sep 2, 2021 | — |
Zoning review Planning · CP-ZOC | Jan 13, 2021 | Jan 28, 2021 | — |
Disability access review Mayor's Office on Disability · MOD | Jan 13, 2021 | Oct 4, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Jan 14, 2021 | Jun 1, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 19, 2021 | Dec 13, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 20, 2021 | Sep 21, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 20, 2021 | Sep 22, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 3, 2021 | Nov 22, 2021 | — |
Fire prevention review Fire Department · SFFD | Nov 3, 2021 | Dec 8, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2021 | Nov 3, 2021 | — |
Disability access review Mayor's Office on Disability · MOD | Nov 3, 2021 | Nov 15, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 21, 2022 | Jul 26, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 21, 2022 | Jul 28, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2022 | Jul 29, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jul 28, 2022 | Jul 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2022 | Aug 4, 2022 | — |
Addendum 3: Withdrawn - mod (including signage)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 13, 2021 | Jan 13, 2021 | — |
Disability access review Mayor's Office on Disability · MOD | Jan 13, 2021 | In progress | — |
Building plan review Building Inspection · BLDG | Jan 13, 2021 | Feb 19, 2021 | — |
Fire prevention review Fire Department · SFFD | Jan 13, 2021 | In progress | — |
Permit Processing Center Building Inspection · PPC | Jan 13, 2021 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 14, 2021 | In progress | — |
Central Permit Bureau Building Inspection · CPB | Jun 11, 2021 | Jun 11, 2021 | — |
Addendum 4: Fire sprinkler
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 22, 2021 | Jul 30, 2021 | — |
Fire prevention review Fire Department · SFFD | Jul 30, 2021 | Jan 18, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 30, 2021 | Jul 21, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 30, 2021 | Jul 25, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 8, 2021 | Jan 18, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2022 | Jul 28, 2022 | — |
Addendum 5: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Fire prevention review Fire Department · SFFD | Jun 16, 2023 | Jun 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 16, 2023 | Jun 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 16, 2023 | Jun 21, 2023 | — |
Addendum 6: Photovoltaics
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 25, 2023 | Jul 25, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 25, 2023 | Aug 25, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2023 | Sep 5, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jul 25, 2023 | Aug 8, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 25, 2023 | Nov 6, 2023 | Administrative |
Electrical plan review Building Inspection · MECH-E | Jul 31, 2023 | Aug 7, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 26, 2023 | Oct 11, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 26, 2023 | Sep 26, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2023 | Oct 19, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 26, 2023 | Sep 28, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 28, 2023 | Sep 28, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 6, 2023 | Nov 15, 2023 | Administrative |
Addendum 7: Emergency responder radio coverage system (errc)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 27, 2022 | Dec 27, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 4, 2023 | Jan 25, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 30, 2023 | Jan 30, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2023 | Feb 2, 2023 | — |
Addendum 8: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 24, 2022 | May 24, 2022 | — |
Zoning review Planning · CP-ZOC | May 24, 2022 | Jul 7, 2022 | — |
Building plan review Building Inspection · BLDG | May 24, 2022 | Jul 11, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 24, 2022 | May 25, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 24, 2022 | Jul 14, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2022 | Jul 22, 2022 | — |
Addendum 9: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Public health review Public Health · HEALTH | May 13, 2021 | May 13, 2021 | — |
Central Permit Bureau Building Inspection · CPB | May 27, 2021 | May 27, 2021 | — |
Permit Processing Center Building Inspection · PPC | May 27, 2021 | May 28, 2021 | — |
Central Permit Bureau Building Inspection · CPB | May 28, 2021 | May 31, 2022 | — |
Addendum 10: F/a two-way communication system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 8, 2023 | Jun 8, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 16, 2023 | Jun 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 16, 2023 | Jun 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 16, 2023 | Jun 21, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $30,000,000
| Name | Role | License on permit |
|---|---|---|
| Karen E Murray | Architect | C27052 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026