5 Embarcadero Center
San Francisco permit 202005067339 · Financial District/South Beach
At&t modification: install 4 new 5g antennas on new pipe mounts; swap 3 extg antennas with 3 new antennas; remove 6 extg rrus & install 3 new rrus; install other small equipment; install new fiber. no change to extg batteries.
- Filed
- May 6, 2020
- Issued
- Jan 4, 2021 (8 months after filing)
- Completed
- Not completed yet
- Review stops
- 7 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 6, 2020 | May 6, 2020 | — |
Permit Processing Center Building Inspection · PPC | May 18, 2020 | Sep 17, 2020 | — |
Zoning review Planning · CP-ZOC | May 20, 2020 | Aug 3, 2020 | — |
Building plan review Building Inspection · BLDG | May 20, 2020 | Sep 9, 2020 | — |
Fire prevention review Fire Department · SFFD | May 20, 2020 | Aug 3, 2020 | — |
Public health review Public Health · HEALTH | May 20, 2020 | Sep 16, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Sep 17, 2020 | Jan 4, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $24,000
| Name | Role | License on permit |
|---|---|---|
| Amer Alkloub Pramira | Engineer | C90995 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026