490 Collingwood St
San Francisco permit 202006038108 · Noe Valley
New two additional dwelling units at ground floor per ordinance 162-16. unit a 322 sq ft gross and unit b 307 sq ft gross. sprinkler entire ground flr, manual fire alarm system shall be provided throughout entire bldg.
- Filed
- Jun 3, 2020
- Issued
- Jun 12, 2024 (48 months after filing)
- Completed
- Not completed yet
- Review stops
- 54 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Public Utilities
- Put on hold
- 14 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 3, 2020 | Aug 7, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 7, 2020 | May 30, 2024 | Administrative |
Planning pre-screening Planning · PRE-PLN | Aug 11, 2020 | Aug 11, 2020 | — |
Fire pre-screening Fire Department · PRE-FIRE | Aug 11, 2020 | Aug 13, 2020 | — |
Zoning review Planning · CP-ZOC | Aug 18, 2020 | Nov 17, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 18, 2020 | Oct 15, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 18, 2020 | Aug 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 18, 2020 | Mar 10, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 18, 2020 | Aug 20, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2020 | Oct 18, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 18, 2020 | Sep 8, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Sep 16, 2020 | Mar 7, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Sep 16, 2020 | Dec 26, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Feb 2, 2022 | Feb 2, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2022 | Feb 8, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 22, 2022 | Nov 21, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 6, 2022 | Apr 15, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Oct 18, 2022 | Jan 8, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 18, 2022 | Oct 18, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 18, 2022 | Oct 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2022 | Oct 19, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 21, 2022 | Feb 23, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 9, 2023 | Mar 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 17, 2023 | Mar 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 20, 2023 | Mar 20, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 2, 2023 | Aug 2, 2023 | Issued Comments |
Planning neighborhood notice Planning · CP-NP | Aug 4, 2023 | Aug 4, 2023 | Administrative |
Planning discretionary review Planning · CP-DR | Aug 22, 2023 | Aug 30, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2023 | Oct 25, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 26, 2023 | Oct 26, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 15, 2023 | Dec 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2023 | Dec 19, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 15, 2023 | Dec 18, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2023 | Dec 26, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2023 | Dec 18, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Jan 10, 2024 | Apr 16, 2024 | Administrative |
Building inspector Building Inspection · BID-INSP | Jan 10, 2024 | Jan 10, 2024 | Approved |
Code enforcement Building Inspection · CES | Jan 10, 2024 | Jan 10, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 23, 2024 | Apr 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 23, 2024 | May 7, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 23, 2024 | Apr 29, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 23, 2024 | Apr 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 23, 2024 | Apr 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 23, 2024 | Apr 24, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 23, 2024 | Apr 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 15, 2024 | May 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 15, 2024 | May 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2024 | May 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 15, 2024 | May 20, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 15, 2024 | May 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 15, 2024 | May 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2024 | May 28, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 28, 2024 | May 28, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 30, 2024 | Jun 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $206,086
| Name | Role | License on permit |
|---|---|---|
| Philip Whitehead | Engineer | C30996 |
| Rodrigo Santos Rs Engineering | Engineer | S2984 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025