658 Shotwell St
San Francisco permit 202007079721 · Mission
Priority processing. interior and exterior renovation, including foundation replacement and new resident and employee bathrooms. reconfiguration of bedrooms to accommodate increased client count.
- Filed
- Jul 7, 2020
- Issued
- Jan 15, 2021 (6 months after filing)
- Completed
- Aug 1, 2022 (18 months after issuance)
- Review stops
- 24 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 7, 2020 | Dec 2, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jul 14, 2020 | Jan 14, 2021 | — |
Planning pre-screening Planning · PRE-PLN | Jul 20, 2020 | Jul 21, 2020 | — |
Fire pre-screening Fire Department · PRE-FIRE | Jul 20, 2020 | Jul 20, 2020 | — |
Fire prevention review Fire Department · SFFD | Jul 20, 2020 | Dec 21, 2020 | — |
Public Works pre-screening Public Works · PRE-DPW | Aug 18, 2020 | Aug 26, 2020 | — |
Zoning review Planning · CP-ZOC | Aug 26, 2020 | Dec 23, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 26, 2020 | Dec 2, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Aug 26, 2020 | Dec 15, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 26, 2020 | Dec 23, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Aug 26, 2020 | Dec 30, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 26, 2020 | Jan 11, 2021 | — |
Public health review Public Health · HEALTH | Aug 26, 2020 | Nov 24, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Aug 27, 2020 | Sep 3, 2020 | — |
Building plan review Building Inspection · BLDG | Dec 21, 2020 | Dec 28, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 21, 2020 | Jan 11, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Dec 21, 2020 | Jan 8, 2021 | — |
Public health review Public Health · HEALTH | Dec 21, 2020 | Jan 5, 2021 | — |
Fire prevention review Fire Department · SFFD | Jan 8, 2021 | Jan 8, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 11, 2021 | Jan 13, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 11, 2021 | Jan 11, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jan 11, 2021 | Jan 11, 2021 | — |
Public health review Public Health · HEALTH | Jan 11, 2021 | Jan 12, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jan 14, 2021 | Jan 15, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,050,000
| Name | Role | License on permit |
|---|---|---|
| Ian R Dunn Openscope Studio Inc | Architect | 27241 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022