228 Vicksburg St
San Francisco permit 202007099901 · Noe Valley
To erect a 4 stories, 3 unit condos, type-v-a bldg.
- Filed
- Jul 9, 2020
- Issued
- Mar 13, 2023 (32 months after filing)
- Completed
- Aug 21, 2025 (29 months after issuance)
- Review stops
- 49 stops across 5 departments
- Comments issued
- 12 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 11 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 17, 2020 | Aug 19, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 19, 2020 | Feb 14, 2023 | — |
Planning pre-screening Planning · PRE-PLN | Aug 24, 2020 | Aug 26, 2020 | — |
Building pre-screening Building Inspection · PRE-BLDG | Aug 24, 2020 | Sep 8, 2020 | — |
Fire pre-screening Fire Department · PRE-FIRE | Aug 24, 2020 | Aug 26, 2020 | — |
Zoning review Planning · CP-ZOC | Sep 9, 2020 | Sep 21, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 9, 2020 | Sep 9, 2020 | — |
Building plan review Building Inspection · BLDG | Dec 14, 2020 | Jan 13, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 22, 2022 | Nov 29, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 22, 2022 | Dec 22, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2022 | Oct 24, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 20, 2023 | Feb 3, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 20, 2023 | Jan 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 20, 2023 | Jan 23, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 20, 2023 | Jan 25, 2023 | — |
Development fee collection Building Inspection · DFCU | Feb 14, 2023 | Feb 14, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 14, 2023 | Mar 13, 2023 | — |
Addendum 1: Shoring, foundations, structural, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 24, 2023 | Apr 10, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 10, 2023 | May 31, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2023 | May 10, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 10, 2023 | Mar 1, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Apr 12, 2023 | Feb 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 1, 2024 | Mar 12, 2024 | Administrative |
Addendum 2: Arch, mep, greenpoint, energy
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 24, 2023 | Apr 10, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 10, 2023 | Aug 11, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2023 | Aug 2, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 10, 2023 | Aug 9, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2023 | Feb 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2023 | Apr 19, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 10, 2023 | Jan 19, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 10, 2023 | Mar 20, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Apr 12, 2023 | May 9, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 17, 2023 | Apr 18, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 2, 2023 | Aug 2, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 30, 2023 | Aug 30, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 18, 2023 | Sep 28, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 18, 2023 | Oct 18, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2023 | Nov 6, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 22, 2023 | Nov 22, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Nov 29, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 30, 2023 | Dec 11, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 19, 2023 | Dec 19, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2023 | Dec 26, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 2, 2024 | Jan 2, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Feb 23, 2024 | Mar 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 23, 2024 | Feb 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 26, 2024 | Feb 26, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Mar 14, 2024 | Mar 14, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2024 | Mar 21, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $1,195,290
| Name | Role | License on permit |
|---|---|---|
| Earle Edward Weiss E.E. Weiss Architects, Inc. | Architect | C22416 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026