1524 Polk St
San Francisco permit 202007140159 · Nob Hill
Hvac replacement on roof: remove e cu 1,2 and ahu 1,2. new cu1,2 and ahu 1,2 per attached schedule, install electrical system, remove all duets system from mezzanine
- Filed
- Jul 14, 2020
- Issued
- Feb 2, 2021 (7 months after filing)
- Completed
- Jun 14, 2022 (16 months after issuance)
- Review stops
- 16 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 14, 2020 | Jul 14, 2020 | — |
Zoning review Planning · CP-ZOC | Jul 15, 2020 | Jul 15, 2020 | — |
Building plan review Building Inspection · BLDG | Jul 15, 2020 | Sep 21, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2020 | Jul 15, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Jul 15, 2020 | Jul 15, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Jul 16, 2020 | Sep 17, 2020 | — |
Structural plan approval Building Inspection · PAD-STR | Sep 21, 2020 | Sep 21, 2020 | — |
Fire prevention review Fire Department · SFFD | Sep 29, 2020 | Sep 29, 2020 | — |
Public health review Public Health · HEALTH | Oct 2, 2020 | Jan 7, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Oct 26, 2020 | Nov 17, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 19, 2020 | Nov 19, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Nov 20, 2020 | Nov 20, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Nov 23, 2020 | Dec 21, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Dec 22, 2020 | Dec 22, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 8, 2021 | Feb 2, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 1, 2021 | Feb 1, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $15,000
| Name | Role | License on permit |
|---|---|---|
| Kenneth K Tang | Engineer | C62650 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026