531 Bryant St
San Francisco permit 202007170412 · South of Market
To erect 6 stories, no basement, type i-b, mixed use office building. (b,m,a-3,s-2) ** maher: exempted - approval from dph attached **
- Filed
- Jul 17, 2020
- Issued
- Jul 22, 2021 (12 months after filing)
- Completed
- Not completed yet
- Review stops
- 89 stops across 6 departments
- Comments issued
- None
- Put on hold
- 22 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 21, 2020 | Jul 21, 2020 | — |
Zoning review Planning · CP-ZOC | Jul 21, 2020 | May 27, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 3, 2020 | Jun 4, 2021 | — |
Fire prevention review Fire Department · SFFD | Sep 3, 2020 | Jun 10, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2021 | Jun 11, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 31, 2021 | Apr 15, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 14, 2021 | Jun 23, 2021 | — |
Development fee collection Building Inspection · DFCU | Jun 23, 2021 | Jun 23, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jun 24, 2021 | Jun 24, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jun 24, 2021 | Jul 22, 2021 | — |
Addendum 1: Deep foundation, foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 29, 2021 | Jul 29, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 29, 2021 | May 10, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2021 | Jun 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jun 29, 2022 | Jun 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 29, 2022 | Jul 13, 2022 | — |
Addendum 2: Architectural, mechanical, electrical and plumbing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 29, 2021 | Jul 29, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 29, 2021 | Oct 4, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 23, 2021 | Oct 19, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Aug 30, 2021 | Feb 4, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 23, 2021 | Jan 21, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 23, 2022 | Jan 19, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 23, 2022 | Jan 19, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 6, 2022 | Mar 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 6, 2022 | Oct 13, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 14, 2023 | Feb 14, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 14, 2023 | Feb 17, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 17, 2023 | Feb 27, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 24, 2023 | Feb 24, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2023 | Mar 6, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 8, 2023 | Mar 9, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 13, 2023 | Mar 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 21, 2023 | Mar 21, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2023 | Mar 23, 2023 | — |
Addendum 3: Stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 20, 2022 | Sep 21, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Sep 21, 2022 | Dec 22, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 22, 2022 | Dec 22, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 22, 2022 | Dec 27, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 27, 2022 | Jan 11, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 12, 2023 | Jan 25, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 25, 2023 | Jan 27, 2023 | — |
Addendum 4: Window wall
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 12, 2022 | Dec 12, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 12, 2022 | May 1, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 27, 2023 | May 12, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 20, 2023 | Mar 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 23, 2023 | May 16, 2023 | — |
Zoning review Planning · CP-ZOC | May 18, 2023 | May 25, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 1, 2023 | Jun 1, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 1, 2023 | Jun 2, 2023 | — |
Addendum 5: Fire sprinkler and underground
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 6, 2022 | Jun 6, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 6, 2022 | Aug 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2022 | Aug 24, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 25, 2022 | Aug 25, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 25, 2022 | Aug 31, 2022 | — |
Addendum 6: Fire alarm, elevator landing&2way emergency comm system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 25, 2023 | Apr 25, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 25, 2023 | Jun 19, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 20, 2023 | Jun 20, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 20, 2023 | Jun 21, 2023 | — |
Addendum 7: Generator fuel, oil and piping
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 17, 2022 | Aug 17, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2022 | Sep 14, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Sep 14, 2022 | Jun 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 30, 2022 | Apr 6, 2023 | — |
Fire prevention review Fire Department · SFFD | May 19, 2023 | Jun 7, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 12, 2023 | Jun 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2023 | Jun 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 13, 2023 | Jun 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2023 | Jun 14, 2023 | — |
Addendum 8: Stormwater
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 24, 2022 | Jun 24, 2022 | — |
Plumbing plan check Building Inspection · PID-PC | Jun 27, 2022 | Jul 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 29, 2022 | Jul 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 29, 2022 | Aug 1, 2022 | — |
Addendum 9: Errcs- emergency responder radio coverage system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 17, 2022 | Aug 17, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 26, 2022 | Aug 31, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 1, 2022 | Sep 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 2, 2022 | Sep 8, 2022 | — |
Addendum 10: Ebm-exterior building maintance
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 8, 2023 | Mar 8, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 8, 2023 | Jul 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 15, 2023 | Jun 16, 2023 | Approved |
Zoning review Planning · CP-ZOC | Jul 13, 2023 | Jul 27, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 28, 2023 | Aug 1, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2023 | Aug 3, 2023 | Administrative |
Addendum 11: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 20, 2023 | Jan 20, 2023 | — |
Public health review Public Health · HEALTH | Jan 23, 2023 | Jan 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 24, 2023 | Jan 24, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 24, 2023 | Jan 24, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 24, 2023 | Jan 25, 2023 | — |
Addendum 12: Evacuation signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 4, 2023 | May 4, 2023 | — |
Fire prevention review Fire Department · SFFD | May 4, 2023 | Jun 21, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 21, 2023 | Jun 21, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 21, 2023 | Jun 22, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $14,000,000
| Name | Role | License on permit |
|---|---|---|
| Glenn G Rescalvo Handel Architects,Llp | Architect | C-27080 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026