2531 Polk St
San Francisco permit 202007230750 · Russian Hill
2nd means of egress stair in kind there are 2 sets of stairs-identical at the side rear of building. they start outside then go inside to service the units in the back of the building.
- Filed
- Jul 23, 2020
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 24, 2020 | Jul 24, 2020 | — |
Planning pre-screening Planning · PRE-PLN | Aug 3, 2020 | Aug 4, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 3, 2020 | In progress | — |
Zoning review Planning · CP-ZOC | Aug 27, 2020 | Dec 30, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 27, 2020 | Jan 6, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 27, 2020 | Oct 22, 2020 | — |
Fire prevention review Fire Department · SFFD | Oct 22, 2020 | Oct 22, 2020 | — |
Zoning review Planning · CP-ZOC | Dec 20, 2022 | Dec 21, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 20, 2022 | In progress | — |
Fire prevention review Fire Department · SFFD | Dec 20, 2022 | Dec 21, 2022 | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $15,000
| Name | Role | License on permit |
|---|---|---|
| Cecil W Swason Cecil Swason Archtect | Architect | C8991 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025