As written on the permit application.

To erect 4 stories, no basement, type v-a, 3 units apartments.

Timeline
Key dates from the city record.
Filed
Jul 29, 2020
Issued
Jan 20, 2023 (30 months after filing)
Completed
May 8, 2025 (28 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
37 stops across 6 departments
Comments issued
None
Put on hold
17 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 25, 2020—

Permit Processing Center

Building Inspection · PPC

Jul 13, 2022—

Planning pre-screening

Planning · PRE-PLN

Aug 29, 2020—

Building pre-screening

Building Inspection · PRE-BLDG

Aug 27, 2020—

Fire pre-screening

Fire Department · PRE-FIRE

Aug 27, 2020—

Public Works pre-screening

Public Works · PRE-DPW

Aug 28, 2020—

Permit Center

Permit Center · PERMIT-CTR

Nov 18, 2021—

Zoning review

Planning · CP-ZOC

Dec 3, 2021—

Building plan review

Building Inspection · BLDG

May 19, 2022—

Fire prevention review

Fire Department · SFFD

Jun 2, 2022—

Street use and mapping

Public Works · DPW-BSM

Apr 8, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

May 2, 2022—

Street use and mapping

Public Works · DPW-BSM

Jun 3, 2022—

Urban forestry

Public Works · DPW-BUF

Jun 15, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 28, 2022—

Zoning review

Planning · CP-ZOC

Jun 30, 2022—

Urban forestry

Public Works · DPW-BUF

Jul 20, 2022—

Central Permit Bureau

Building Inspection · CPB

Jan 20, 2023—

Addendum 1: Arch / structural / t-24 / final.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 20, 2023—

Building plan review

Building Inspection · BLDG

May 2, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Apr 28, 2023—

Electrical plan review

Building Inspection · MECH-E

May 1, 2023—

Fire prevention review

Fire Department · SFFD

Jul 6, 2023—

Building plan review

Building Inspection · BLDG

May 8, 2023—

Electrical plan review

Building Inspection · MECH-E

May 16, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 11, 2023—

Street use and mapping

Public Works · DPW-BSM

May 18, 2023—

Urban forestry

Public Works · DPW-BUF

May 31, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 1, 2023—

Building plan review

Building Inspection · BLDG

Jul 5, 2023—

Electrical plan review

Building Inspection · MECH-E

Jul 7, 2023—

Street use and mapping

Public Works · DPW-BSM

Jul 13, 2023—

Zoning review

Planning · CP-ZOC

Jul 19, 2023—

Zoning review

Planning · CP-ZOC

Jul 25, 2023—

Urban forestry

Public Works · DPW-BUF

Jul 28, 2023Approved

Permit Processing Center

Building Inspection · PPC

Jul 31, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 2, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Complete
Estimated cost
$2,420,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael James Hennessey

Michael Hennessey Architecture

ArchitectC31229
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202007290911 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record