1 Front St
San Francisco permit 202007310988 · Financial District/South Beach
First bank of republic at g/f: establish/legalize cafe. construct new partitions at ceiling height & full height. new door frames & hardware. new electrical/data outlets. (e) mech system to remain. new finishes, typical throughout. modified (e) sprinkler system/(e) fls system under sep permit.
- Filed
- Jul 31, 2020
- Issued
- Jul 26, 2022 (24 months after filing)
- Completed
- Not completed yet
- Review stops
- 19 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 31, 2020 | Aug 6, 2020 | — |
Zoning review Planning · CP-ZOC | Aug 10, 2020 | Aug 12, 2020 | — |
Building plan review Building Inspection · BLDG | Aug 10, 2020 | May 3, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Aug 10, 2020 | Apr 6, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2020 | Apr 5, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 10, 2020 | Apr 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2020 | May 10, 2022 | — |
Public health review Public Health · HEALTH | Aug 10, 2020 | Apr 6, 2021 | — |
Permit Processing Center Building Inspection · PPC | Aug 10, 2020 | May 24, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 2, 2021 | May 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2021 | Sep 20, 2021 | — |
Electrical plan review Building Inspection · MECH-E | Sep 9, 2021 | Jan 3, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 9, 2021 | Sep 13, 2021 | — |
Public health review Public Health · HEALTH | Sep 9, 2021 | May 13, 2022 | — |
Building plan review Building Inspection · BLDG | May 3, 2022 | May 3, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 3, 2022 | May 4, 2022 | — |
Electrical plan review Building Inspection · MECH-E | May 3, 2022 | May 12, 2022 | — |
Fire prevention review Fire Department · SFFD | May 3, 2022 | May 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 24, 2022 | Jul 26, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $87,782
| Name | Role | License on permit |
|---|---|---|
| Wesley Tatsuo Fukumori Fbor: Architectural Design | Architect | C14016 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026