Scope of work
As written on the permit application.

Demolish the existing second floor deck and stairs at the back of the home. construct a new 287sf ground floor addition with a roof deck over living and a 42 sf addition on the second floor. no work visible from the street and no increase in height is proposed.

Timeline
Key dates from the city record.
Filed
Aug 5, 2020
Issued
Sep 29, 2021 (14 months after filing)
Completed
Jul 30, 2024 (34 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 4 departments
Comments issued
Not recorded for this permit
Put on hold
4 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 17, 2020—

Planning pre-screening

Planning · PRE-PLN

Aug 28, 2020—

Permit Processing Center

Building Inspection · PPC

Sep 15, 2021—

Zoning review

Planning · CP-ZOC

May 7, 2021—

Planning neighborhood notice

Planning · CP-NP

Mar 12, 2021—

Building plan review

Building Inspection · BLDG

Aug 20, 2021—

Street use and mapping

Public Works · DPW-BSM

May 25, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 28, 2021—

Street use and mapping

Public Works · DPW-BSM

Jun 16, 2021—

Zoning review

Planning · CP-ZOC

Sep 14, 2021—

Street use and mapping

Public Works · DPW-BSM

Jul 21, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 21, 2021—

Street use and mapping

Public Works · DPW-BSM

Sep 15, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 26, 2021—

Central Permit Bureau

Building Inspection · CPB

Sep 29, 2021—

Addendum 1: Final

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 15, 2021—

Building plan review

Building Inspection · BLDG

Nov 23, 2021—

Mechanical and energy plan review

Building Inspection · MECH

Nov 30, 2021—

Street use and mapping

Public Works · DPW-BSM

Oct 22, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 27, 2021—

Permit Processing Center

Building Inspection · PPC

Dec 14, 2021—

Street use and mapping

Public Works · DPW-BSM

Nov 22, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Nov 15, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Nov 23, 2021—

Building plan review

Building Inspection · BLDG

Dec 10, 2021—

Street use and mapping

Public Works · DPW-BSM

Dec 14, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Dec 7, 2021—

Central Permit Bureau

Building Inspection · CPB

Dec 15, 2021—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$150,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jeff Alan Gard

Jeff Alan Gard Architect

ArchitectC30906
Kevin Gerard O'connor

Kevin O'connor Inc.

EngineerC-65297
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202008051158 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record