236 Clipper St
San Francisco permit 202008051158 · Noe Valley
Demolish the existing second floor deck and stairs at the back of the home. construct a new 287sf ground floor addition with a roof deck over living and a 42 sf addition on the second floor. no work visible from the street and no increase in height is proposed.
- Filed
- Aug 5, 2020
- Issued
- Sep 29, 2021 (14 months after filing)
- Completed
- Jul 30, 2024 (34 months after issuance)
- Review stops
- 28 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 5, 2020 | Aug 17, 2020 | — |
Planning pre-screening Planning · PRE-PLN | Aug 6, 2020 | Aug 28, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 6, 2020 | Sep 15, 2021 | — |
Zoning review Planning · CP-ZOC | Sep 1, 2020 | May 7, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Jan 29, 2021 | Mar 12, 2021 | — |
Building plan review Building Inspection · BLDG | May 7, 2021 | Aug 20, 2021 | — |
Street use and mapping Public Works · DPW-BSM | May 7, 2021 | May 25, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 7, 2021 | Jun 28, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 16, 2021 | Jun 16, 2021 | — |
Zoning review Planning · CP-ZOC | Jun 16, 2021 | Sep 14, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2021 | Jul 21, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 20, 2021 | Jul 21, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2021 | Sep 15, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2021 | Aug 26, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 15, 2021 | Sep 29, 2021 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 14, 2021 | Oct 15, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 16, 2021 | Nov 23, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2021 | Nov 30, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2021 | Oct 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2021 | Oct 27, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 16, 2021 | Dec 14, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2021 | Nov 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2021 | Nov 15, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2021 | Nov 23, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 1, 2021 | Dec 10, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Dec 1, 2021 | Dec 14, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2021 | Dec 7, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Dec 14, 2021 | Dec 15, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Jeff Alan Gard Jeff Alan Gard Architect | Architect | C30906 |
| Kevin Gerard O'connor Kevin O'connor Inc. | Engineer | C-65297 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025