185 Berry St
San Francisco permit 202008061213 · Mission Bay
At&t modification: remove(6)(e)antennas & frp screens from north facade & install(13)(n)antennas on rooftop screening within(3)(n) frp scn boxes; relocate(e)equipment area from northern rooftop to s rooftop near(n)antenna location, screened within(e)mechanical scn wall; install(12)(n)batteries @
- Filed
- Aug 6, 2020
- Issued
- Dec 2, 2020 (4 months after filing)
- Completed
- Feb 10, 2022 (14 months after issuance)
- Review stops
- 10 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 6, 2020 | Sep 4, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 4, 2020 | Oct 31, 2020 | — |
Planning pre-screening Planning · PRE-PLN | Sep 9, 2020 | Sep 10, 2020 | — |
Fire pre-screening Fire Department · PRE-FIRE | Sep 9, 2020 | Sep 16, 2020 | — |
Zoning review Planning · CP-ZOC | Sep 16, 2020 | Sep 29, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 16, 2020 | Sep 18, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2020 | Sep 23, 2020 | — |
Fire prevention review Fire Department · SFFD | Sep 16, 2020 | Sep 21, 2020 | — |
Public health review Public Health · HEALTH | Sep 16, 2020 | Sep 25, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Oct 31, 2020 | Dec 2, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Amer Alkloub Pramira | Architect | C90995 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026