1522 Howard St
San Francisco permit 202008151923 · Mission
Application for adu in existing ground floor space. new work to include new kitchen, remodel of existing bathroom, and new doors and window out to rear yard. mep, and any required title 24 calcs, permitted separately. per ord 162-16.
- Filed
- Aug 15, 2020
- Issued
- Oct 29, 2021 (14 months after filing)
- Completed
- May 30, 2023 (19 months after issuance)
- Review stops
- 19 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Aug 15, 2020 | Aug 15, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Aug 15, 2020 | Nov 3, 2020 | — |
Permit Processing Center Building Inspection · PPC | Nov 3, 2020 | Sep 16, 2021 | — |
Planning pre-screening Planning · PRE-PLN | Nov 7, 2020 | Nov 24, 2020 | — |
Fire pre-screening Fire Department · PRE-FIRE | Nov 7, 2020 | Nov 10, 2020 | — |
Zoning review Planning · CP-ZOC | Nov 25, 2020 | Feb 1, 2021 | — |
Building plan review Building Inspection · BLDG | Feb 1, 2021 | Apr 26, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2021 | May 12, 2021 | — |
Fire prevention review Fire Department · SFFD | Feb 1, 2021 | Feb 8, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2021 | Feb 1, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2021 | May 5, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2021 | Apr 26, 2021 | — |
Zoning review Planning · CP-ZOC | May 4, 2021 | May 4, 2021 | — |
Street use and mapping Public Works · DPW-BSM | May 4, 2021 | May 4, 2021 | — |
Building plan review Building Inspection · BLDG | May 13, 2021 | May 14, 2021 | — |
Fire prevention review Fire Department · SFFD | May 13, 2021 | May 14, 2021 | — |
Zoning review Planning · CP-ZOC | May 18, 2021 | Sep 16, 2021 | — |
Development fee collection Building Inspection · DFCU | Sep 16, 2021 | Sep 16, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 16, 2021 | Oct 29, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Michael Frank Zucker Michael Zucker & Associates | Architect | C8820 |
| Jahandar Yadegar Jya Sf Structural Engineers | Engineer | 2871 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026