139 Pierce St
San Francisco permit 202008212282 · Haight Ashbury
Create new roof deck & penthouse. build new penthouse for roof deck access. build new roof deck limited to 250 sq ft to allow for minimal structural upgrades. roof deck is for use of owners unit only.
- Filed
- Aug 21, 2020
- Issued
- Oct 19, 2021 (14 months after filing)
- Completed
- Not completed yet
- Review stops
- 38 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 11 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 21, 2020 | Oct 1, 2020 | — |
Permit Processing Center Building Inspection · PPC | Oct 1, 2020 | Sep 29, 2021 | — |
Fire pre-screening Fire Department · PRE-FIRE | Nov 9, 2020 | Nov 13, 2020 | — |
Zoning review Planning · CP-ZOC | Nov 18, 2020 | Apr 2, 2021 | — |
Zoning review Planning · CP-ZOC | Apr 2, 2021 | Apr 2, 2021 | — |
Building plan review Building Inspection · BLDG | May 4, 2021 | Jul 12, 2021 | — |
Street use and mapping Public Works · DPW-BSM | May 4, 2021 | May 6, 2021 | — |
Fire prevention review Fire Department · SFFD | May 4, 2021 | Jul 20, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 4, 2021 | Jun 23, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2021 | Jul 14, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 12, 2021 | Sep 28, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 14, 2021 | Jul 15, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2021 | Oct 19, 2021 | — |
Addendum 1: Structural/arch/mep/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 21, 2021 | Oct 21, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 21, 2021 | Dec 28, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 25, 2021 | Jan 7, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 25, 2021 | Mar 16, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2021 | Jul 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2021 | Jul 29, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 25, 2021 | Jan 3, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 16, 2022 | Oct 31, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 1, 2022 | Jul 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 5, 2022 | Sep 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 16, 2022 | Oct 19, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2022 | Sep 29, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2022 | Sep 28, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 27, 2022 | Sep 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 19, 2022 | Nov 14, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 31, 2022 | Nov 7, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2022 | Oct 31, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2022 | Nov 9, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2022 | Nov 2, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 14, 2022 | Dec 23, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 23, 2022 | Nov 28, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 23, 2022 | Nov 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 23, 2022 | Dec 28, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 23, 2022 | Nov 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 28, 2022 | Jan 5, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Laurie Jo Erickson Erickson Zebroski Design Grp | Architect | C-24082 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026