San Francisco permit 202008212293 · Noe Valley

AdditionFull plan reviewIssued
Street view · May 2022
Google Street View of 1434 Dolores St, May 2022
Scope of work
As written on the permit application.

Vertical addition containing new master suite at 3rd flr. horizontal addition at rear of 1st flr. provide new stair at front of building and new deck at rear of building. provide seismic upgrade and new fire sprinkler system throughout (sprinkler on separate submittal).

Timeline
Key dates from the city record.
Filed
Aug 21, 2020
Issued
Sep 13, 2021 (13 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 5 departments
Comments issued
Not recorded for this permit
Put on hold
9 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 21, 2020—

Zoning review

Planning · CP-ZOC

Mar 11, 2021—

Permit Processing Center

Building Inspection · PPC

Sep 1, 2021—

Planning neighborhood notice

Planning · CP-NP

Mar 11, 2021—

Building plan review

Building Inspection · BLDG

Jul 27, 2021—

Mechanical and energy plan review

Building Inspection · MECH

Aug 17, 2021—

Fire prevention review

Fire Department · SFFD

May 7, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 16, 2021—

Street use and mapping

Public Works · DPW-BSM

Aug 19, 2021—

Urban forestry

Public Works · DPW-BUF

Aug 6, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 5, 2021—

Fire prevention review

Fire Department · SFFD

Aug 17, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 18, 2021—

Building plan review

Building Inspection · BLDG

Aug 26, 2021—

Urban forestry

Public Works · DPW-BUF

Aug 30, 2021—

Central Permit Bureau

Building Inspection · CPB

Sep 13, 2021—

Addendum 1: Final plan

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 29, 2021—

Building plan review

Building Inspection · BLDG

Apr 13, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Nov 15, 2021—

Street use and mapping

Public Works · DPW-BSM

Jan 20, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 31, 2022—

Permit Processing Center

Building Inspection · PPC

Aug 5, 2022—

Building plan review

Building Inspection · BLDG

Jul 28, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Jun 15, 2022—

Street use and mapping

Public Works · DPW-BSM

May 11, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 15, 2022—

Street use and mapping

Public Works · DPW-BSM

Jul 29, 2022—

Central Permit Bureau

Building Inspection · CPB

Aug 8, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$483,836
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael James Hennessey

Michael Hennessey Architecture

ArchitectC31229
Stan Michael Wu

Smw & Associates, Inc.

Engineer4665
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202008212293 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record