San Francisco permit 202008222423 · Bernal Heights

AdditionFull plan reviewComplete
Street view · Jul 2015
Google Street View of 480 Andover St, Jul 2015
Scope of work
As written on the permit application.

Adding a new 3rd floor on an exisitng 2-story bldg. exterior renovation on the facade of the bldg. new grand room at the 1st flr w/ a new wet bar and full bathroom. the new added 3rd flr will be furnished w/ one master suite and 2 bedrooms.

Timeline
Key dates from the city record.
Filed
Aug 22, 2020
Issued
Feb 6, 2023 (30 months after filing)
Completed
Dec 11, 2024 (22 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
25 stops across 4 departments
Comments issued
None
Put on hold
7 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 27, 2020—

Permit Processing Center

Building Inspection · PPC

Feb 1, 2023—

Planning pre-screening

Planning · PRE-PLN

Sep 1, 2020—

Building pre-screening

Building Inspection · PRE-BLDG

Sep 8, 2020—

Zoning review

Planning · CP-ZOC

Jul 27, 2022—

Planning neighborhood notice

Planning · CP-NP

Jun 3, 2022—

Building plan review

Building Inspection · BLDG

Oct 27, 2022—

Street use and mapping

Public Works · DPW-BSM

Sep 14, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 16, 2022—

Building plan review

Building Inspection · BLDG

Dec 21, 2022—

Building plan review

Building Inspection · BLDG

Dec 21, 2022—

Zoning review

Planning · CP-ZOC

Jan 4, 2023—

Street use and mapping

Public Works · DPW-BSM

Feb 1, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Dec 23, 2022—

Central Permit Bureau

Building Inspection · CPB

Feb 6, 2023—

Addendum 1: Final

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 13, 2023—

Building plan review

Building Inspection · BLDG

Jun 15, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 15, 2023—

Street use and mapping

Public Works · DPW-BSM

Aug 22, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Mar 15, 2023—

Permit Processing Center

Building Inspection · PPC

Aug 31, 2023—

Building plan review

Building Inspection · BLDG

Jun 20, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 22, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 31, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Sep 7, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$491,763
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jack W J Tam

Team 7 International

ArchitectC-11181
Michael Austin Hom

Hom & Pisano Engineering Inc.

Engineer71450
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202008222423 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record