480 Andover St
San Francisco permit 202008222423 · Bernal Heights
Adding a new 3rd floor on an exisitng 2-story bldg. exterior renovation on the facade of the bldg. new grand room at the 1st flr w/ a new wet bar and full bathroom. the new added 3rd flr will be furnished w/ one master suite and 2 bedrooms.
- Filed
- Aug 22, 2020
- Issued
- Feb 6, 2023 (30 months after filing)
- Completed
- Dec 11, 2024 (22 months after issuance)
- Review stops
- 25 stops across 4 departments
- Comments issued
- None
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 22, 2020 | Aug 27, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 27, 2020 | Feb 1, 2023 | — |
Planning pre-screening Planning · PRE-PLN | Sep 1, 2020 | Sep 1, 2020 | — |
Building pre-screening Building Inspection · PRE-BLDG | Sep 1, 2020 | Sep 8, 2020 | — |
Zoning review Planning · CP-ZOC | Sep 8, 2020 | Jul 27, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Jun 1, 2022 | Jun 3, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 5, 2022 | Oct 27, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2022 | Sep 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2022 | Aug 16, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 27, 2022 | Dec 21, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 21, 2022 | Dec 21, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 22, 2022 | Jan 4, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 22, 2022 | Feb 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2022 | Dec 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 1, 2023 | Feb 6, 2023 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 13, 2023 | Mar 13, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 14, 2023 | Jun 15, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 14, 2023 | Jun 15, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2023 | Aug 22, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2023 | Mar 15, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 14, 2023 | Aug 31, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 15, 2023 | Jun 20, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 22, 2023 | Jun 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2023 | Aug 31, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2023 | Sep 7, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $491,763
| Name | Role | License on permit |
|---|---|---|
| Jack W J Tam Team 7 International | Architect | C-11181 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jul 2015