242 Liberty St
San Francisco permit 202008252579 · Castro/Upper Market
Vertical and horizontal additions to existing duplex to include: 242 liberty - great room, 3 bedrooms, 3 1/2 baths, media room, laundry, roof deck 244 liberty - great room, 3 bedrooms, 3 1/2 baths, study, laundry, [2] roof decks
- Filed
- Aug 25, 2020
- Issued
- Jun 3, 2026 (69 months after filing)
- Completed
- Not completed yet
- Review stops
- 52 stops across 6 departments
- Comments issued
- 8 times, by Fire Department, Permit Center, Planning, Building Inspection, Public Works
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 25, 2020 | Aug 27, 2020 | — |
Permit Processing Center Building Inspection · PPC | Aug 27, 2020 | May 5, 2026 | Administrative |
Planning pre-screening Planning · PRE-PLN | Sep 1, 2020 | Sep 1, 2020 | — |
Building pre-screening Building Inspection · PRE-BLDG | Sep 1, 2020 | Oct 21, 2020 | — |
Zoning review Planning · CP-ZOC | Oct 21, 2020 | Mar 9, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Aug 31, 2021 | Sep 14, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Feb 8, 2023 | Feb 8, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 9, 2023 | Feb 9, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 14, 2023 | Apr 14, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 14, 2023 | Feb 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 14, 2023 | Mar 24, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 24, 2023 | Sep 12, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Apr 20, 2023 | May 9, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 24, 2023 | Sep 12, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 12, 2023 | Sep 19, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 22, 2023 | Sep 26, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 29, 2023 | Sep 29, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 2, 2023 | Oct 3, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 5, 2023 | Oct 5, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 5, 2023 | Oct 5, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 5, 2023 | Oct 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 5, 2023 | Oct 6, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2023 | Oct 12, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Apr 11, 2024 | Apr 15, 2024 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Apr 23, 2024 | Apr 23, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2024 | Jun 3, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jan 13, 2025 | Apr 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 13, 2025 | Jan 14, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jan 13, 2025 | Jan 15, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 13, 2025 | Jan 14, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2025 | Jan 24, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2025 | Jan 22, 2025 | Approved |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 4, 2026 | Jun 25, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Aug 5, 2026 | Aug 25, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 26, 2026 | Aug 28, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Aug 28, 2026 | Sep 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 28, 2026 | Nov 2, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 28, 2026 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 28, 2026 | Sep 25, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 28, 2026 | Sep 15, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 28, 2026 | Aug 31, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 28, 2026 | Sep 1, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 28, 2026 | Sep 8, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 28, 2026 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Oct 21, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,740,314
| Name | Role | License on permit |
|---|---|---|
| Ryan Francis Knock Knock Arch & Design | Architect | C31156 |
| William Keith Egan Bill Egan Architect | Architect | C9719 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025