2148 16th Av
San Francisco permit 202008252623 · West of Twin Peaks
1 story horizontal addition to add new master suite. remodel e bedrooms and add powder room
- Filed
- Aug 25, 2020
- Issued
- Nov 19, 2021 (15 months after filing)
- Completed
- Not completed yet
- Review stops
- 20 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 25, 2020 | Aug 25, 2020 | — |
Planning pre-screening Planning · PRE-PLN | Sep 1, 2020 | Dec 10, 2020 | — |
Building pre-screening Building Inspection · PRE-BLDG | Sep 1, 2020 | Sep 15, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 1, 2020 | Nov 16, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 15, 2020 | Jan 16, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 29, 2020 | May 19, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 31, 2021 | Apr 6, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | May 24, 2021 | Jun 2, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | May 24, 2021 | Oct 15, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 24, 2021 | Jul 8, 2021 | — |
Building plan review Building Inspection · BLDG | Oct 27, 2021 | Nov 16, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 16, 2021 | Nov 19, 2021 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 20, 2021 | Apr 25, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 19, 2021 | Nov 23, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 23, 2021 | Feb 25, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 23, 2021 | Feb 28, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 23, 2021 | Dec 20, 2021 | — |
Permit Processing Center Building Inspection · PPC | Nov 23, 2021 | Apr 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 4, 2022 | Feb 28, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 28, 2022 | Mar 1, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Charles C Chan Cc Architects Inc | Architect | C31716 |
| Edmond Wong | Engineer | C86522 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019