3833 21st St
San Francisco permit 202008272808 · Noe Valley
Kitchen remodel and expansion to side of house. powder room relocation. renovate & legalize studio unit on ground floor. new foundations throughout.
- Filed
- Aug 27, 2020
- Issued
- Aug 17, 2021 (12 months after filing)
- Completed
- Jan 2, 2025 (41 months after issuance)
- Review stops
- 11 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 27, 2020 | Sep 28, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 28, 2020 | Aug 13, 2021 | — |
Zoning review Planning · CP-ZOC | Nov 20, 2020 | Mar 24, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Feb 1, 2021 | Feb 5, 2021 | — |
Building plan review Building Inspection · BLDG | Mar 24, 2021 | Aug 3, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 24, 2021 | Apr 20, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Mar 24, 2021 | Jul 16, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 24, 2021 | Jul 20, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 9, 2021 | Aug 10, 2021 | — |
Development fee collection Building Inspection · DFCU | Aug 11, 2021 | Aug 13, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 13, 2021 | Aug 17, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Philip Christopher Rossington Rossington Architecture | Architect | C-25251 |
| Shaun Edward Moynahan Semco Engineering Inc. | Engineer | S-4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025