3260 26th St
San Francisco permit 202008313033 · Mission
To erect a type 1b, 7 story, 42 residential unit building with one commertial unit and one partial basement.
- Filed
- Aug 31, 2020
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 27 stops across 7 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department
- Put on hold
- 6 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 31, 2020 | Sep 11, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 11, 2020 | May 14, 2025 | Administrative |
Planning pre-screening Planning · PRE-PLN | Sep 15, 2020 | Sep 17, 2020 | — |
Fire pre-screening Fire Department · PRE-FIRE | Sep 15, 2020 | Sep 22, 2020 | — |
Zoning review Planning · CP-ZOC | Sep 23, 2020 | Nov 14, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 28, 2020 | Jul 9, 2024 | Approved-Stipulated |
CON CON-BOND | Jul 12, 2022 | Jun 23, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | Oct 25, 2022 | Nov 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 21, 2023 | Apr 25, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 21, 2023 | Feb 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 21, 2023 | Mar 12, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 21, 2023 | Apr 21, 2023 | — |
Public health review Public Health · HEALTH | Feb 21, 2023 | Feb 8, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 2, 2023 | Nov 14, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 5, 2024 | Feb 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 7, 2024 | Feb 8, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 29, 2024 | Feb 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2024 | Jun 27, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Nov 14, 2024 | Nov 14, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 14, 2024 | Nov 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 15, 2024 | Nov 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 15, 2024 | Nov 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 18, 2024 | Nov 18, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 27, 2025 | Mar 27, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Apr 10, 2025 | Apr 10, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Apr 16, 2025 | Apr 22, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 14, 2025 | In progress | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Approved
- Estimated cost
- $15,500,000
| Name | Role | License on permit |
|---|---|---|
| Edward Davis Morris Kerman Morris Architects | Architect | C24585 |
| Jeff Brink Gensler | Engineer | S6142 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026