3745 24th St
San Francisco permit 202009013125 · Noe Valley
Add 3 adu's to the ground floor per ordinance 162-16.
- Filed
- Sep 1, 2020
- Issued
- Aug 9, 2022 (23 months after filing)
- Completed
- Nov 27, 2023 (16 months after issuance)
- Review stops
- 29 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 1, 2020 | Sep 10, 2020 | — |
Planning pre-screening Planning · PRE-PLN | Sep 14, 2020 | Dec 11, 2020 | — |
Building pre-screening Building Inspection · PRE-BLDG | Sep 14, 2020 | Dec 8, 2020 | — |
Fire pre-screening Fire Department · PRE-FIRE | Sep 14, 2020 | Sep 16, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 14, 2020 | Feb 25, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 12, 2020 | Jul 29, 2021 | — |
Building plan review Building Inspection · BLDG | Apr 14, 2021 | Aug 11, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 14, 2021 | May 20, 2021 | — |
Fire prevention review Fire Department · SFFD | Apr 14, 2021 | Feb 22, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2021 | Apr 27, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2021 | Apr 16, 2021 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 25, 2021 | Jan 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2021 | Jul 27, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2021 | Jul 21, 2021 | — |
Zoning review Planning · CP-ZOC | Jul 29, 2021 | Oct 13, 2021 | — |
Building plan review Building Inspection · BLDG | Jan 21, 2022 | Jan 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 26, 2022 | Jan 26, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 26, 2022 | Jan 26, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jan 27, 2022 | Feb 18, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 18, 2022 | Feb 23, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 18, 2022 | Feb 22, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 18, 2022 | Feb 24, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2022 | Feb 22, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 18, 2022 | Feb 22, 2022 | — |
Urban forestry Public Works · DPW-BUF | Feb 18, 2022 | Feb 24, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 18, 2022 | Feb 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2022 | Feb 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2022 | Aug 9, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Mar 1, 2022 | Mar 1, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Ian R Dunn Openscope Studio | Architect | C27241 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2019