1857 Church St
San Francisco permit 202009083710 · Glen Park
Kitchen & bath remodel, selective demo & build back (e) spaces. no work to front facade. mep under seperate permit. vertical/horizontal expansion of (e) building envelope. demo rear sunroom structure & construct new 2-story 352 sq ft crate breakfast nook, remodel bathroom, create garden storage area
- Filed
- Sep 8, 2020
- Issued
- Sep 29, 2022 (25 months after filing)
- Completed
- Jul 27, 2023 (10 months after issuance)
- Review stops
- 24 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 8, 2020 | Sep 12, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 12, 2020 | Sep 26, 2022 | — |
Planning pre-screening Planning · PRE-PLN | Sep 15, 2020 | Sep 17, 2020 | — |
Zoning review Planning · CP-ZOC | Sep 18, 2020 | Feb 25, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Jun 29, 2021 | Jun 30, 2021 | — |
Planning discretionary review Planning · CP-DR | Aug 10, 2021 | Feb 23, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 20, 2022 | Sep 23, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 20, 2022 | May 5, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 20, 2022 | Apr 26, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 20, 2022 | May 12, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 1, 2022 | Jun 3, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2022 | Jun 8, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jun 1, 2022 | Jun 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 1, 2022 | Jun 8, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 7, 2022 | Aug 1, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 7, 2022 | Sep 8, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 8, 2022 | Jul 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2022 | Jul 21, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 15, 2022 | Jul 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 15, 2022 | Jul 18, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2022 | Aug 16, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2022 | Sep 14, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 19, 2022 | Sep 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 26, 2022 | Sep 29, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $115,800
| Name | Role | License on permit |
|---|---|---|
| Michael Shad Howard Beazer Studio 22 Design | Architect | C-33524 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2016