As written on the permit application.

Kitchen & bath remodel, selective demo & build back (e) spaces. no work to front facade. mep under seperate permit. vertical/horizontal expansion of (e) building envelope. demo rear sunroom structure & construct new 2-story 352 sq ft crate breakfast nook, remodel bathroom, create garden storage area

Timeline
Key dates from the city record.
Filed
Sep 8, 2020
Issued
Sep 29, 2022 (25 months after filing)
Completed
Jul 27, 2023 (10 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 4 departments
Comments issued
Not recorded for this permit
Put on hold
3 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 12, 2020—

Permit Processing Center

Building Inspection · PPC

Sep 26, 2022—

Planning pre-screening

Planning · PRE-PLN

Sep 17, 2020—

Zoning review

Planning · CP-ZOC

Feb 25, 2022—

Planning neighborhood notice

Planning · CP-NP

Jun 30, 2021—

Planning discretionary review

Planning · CP-DR

Feb 23, 2022—

Building plan review

Building Inspection · BLDG

Sep 23, 2022—

Mechanical and energy plan review

Building Inspection · MECH

May 5, 2022—

Street use and mapping

Public Works · DPW-BSM

Apr 26, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

May 12, 2022—

Zoning review

Planning · CP-ZOC

Jun 3, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Jun 8, 2022—

Street use and mapping

Public Works · DPW-BSM

Jun 8, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 8, 2022—

Structural plan approval

Building Inspection · PAD-STR

Aug 1, 2022—

Structural plan approval

Building Inspection · PAD-STR

Sep 8, 2022—

Zoning review

Planning · CP-ZOC

Jul 22, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Jul 21, 2022—

Street use and mapping

Public Works · DPW-BSM

Jul 20, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 18, 2022—

Street use and mapping

Public Works · DPW-BSM

Aug 16, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Sep 14, 2022—

Building plan review

Building Inspection · BLDG

Sep 23, 2022—

Central Permit Bureau

Building Inspection · CPB

Sep 29, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$115,800
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael Shad Howard Beazer

Studio 22 Design

ArchitectC-33524
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202009083710 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record