3515 Fillmore St
San Francisco permit 202009093733 · Marina
Remodel ground fl at rear of garage to create two new adu's per ordiance 162-6 add access hallway from main entry & (n) posts/bm at garage parking areas. unit a is 495 sf. unit b is 700 sf. unit a is formed from the existing space at the lower level of current unit #107.**maher n/a**
- Filed
- Sep 9, 2020
- Issued
- Nov 8, 2023 (38 months after filing)
- Completed
- Not completed yet
- Review stops
- 20 stops across 5 departments
- Comments issued
- None
- Put on hold
- 7 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 21, 2020 | Oct 31, 2020 | — |
Permit Processing Center Building Inspection · PPC | Oct 31, 2020 | Aug 22, 2023 | — |
Planning pre-screening Planning · PRE-PLN | Dec 16, 2020 | Jul 2, 2021 | — |
Fire pre-screening Fire Department · PRE-FIRE | Dec 16, 2020 | Dec 17, 2020 | — |
Zoning review Planning · CP-ZOC | Jul 6, 2021 | Nov 19, 2021 | — |
Building plan review Building Inspection · BLDG | Aug 11, 2021 | Dec 3, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2021 | Dec 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2021 | Sep 14, 2021 | — |
Fire prevention review Fire Department · SFFD | Aug 11, 2021 | Nov 9, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2021 | Aug 18, 2021 | — |
Urban forestry Public Works · DPW-BUF | Aug 11, 2021 | Aug 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 8, 2021 | Nov 9, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Nov 8, 2021 | Dec 8, 2021 | — |
Zoning review Planning · CP-ZOC | Nov 19, 2021 | Aug 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 23, 2021 | Dec 3, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 23, 2021 | Dec 1, 2021 | — |
Fire prevention review Fire Department · SFFD | Nov 23, 2021 | Dec 3, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2021 | Dec 3, 2021 | — |
Development fee collection Building Inspection · DFCU | Aug 22, 2023 | Aug 22, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 22, 2023 | Nov 8, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $345,000
| Name | Role | License on permit |
|---|---|---|
| Jace Garth Levinson Jace Architecture | Architect | C23075 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025