99 Mississippi St
San Francisco permit 202009124012 · Mission Bay
Wokr on 1st floor only. new entry on 17th st., relace existing windows and doors. refurbish and repaint interior and exterior of building. voluntary lateral force upgrade. existing building 21,287 sq ft, type vb, not sprinklered.
- Filed
- Sep 12, 2020
- Issued
- Feb 2, 2021 (5 months after filing)
- Completed
- Aug 31, 2021 (7 months after issuance)
- Review stops
- 16 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 12, 2020 | Sep 12, 2020 | — |
Zoning review Planning · CP-ZOC | Sep 16, 2020 | Sep 16, 2020 | — |
Building plan review Building Inspection · BLDG | Sep 17, 2020 | Dec 30, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 21, 2020 | Sep 21, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Sep 21, 2020 | Sep 21, 2020 | — |
Fire prevention review Fire Department · SFFD | Sep 22, 2020 | Sep 22, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2020 | Oct 1, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2020 | Jan 13, 2021 | — |
Permit Center Permit Center · PERMIT-CTR | Oct 5, 2020 | Oct 29, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 17, 2020 | Nov 17, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Nov 17, 2020 | Nov 17, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Nov 18, 2020 | Dec 3, 2020 | — |
Permit Center Permit Center · PERMIT-CTR | Dec 10, 2020 | Dec 21, 2020 | — |
Building plan review Building Inspection · BLDG | Dec 30, 2020 | Jan 27, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 11, 2021 | Jan 12, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2021 | Feb 2, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $387,850
| Name | Role | License on permit |
|---|---|---|
| David Nelson Sternberg Sternberg Benjamin Architects | Architect | C11102 |
| David W Kane Harrell Kane Struct Eng Inc | Engineer | S5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026