133 Grand View Av
San Francisco permit 202009234782 · Twin Peaks
2,315 sf horizontal addition to in rear, no change to front facade.
- Filed
- Sep 23, 2020
- Issued
- Mar 28, 2023 (30 months after filing)
- Completed
- Mar 11, 2026 (35 months after issuance)
- Review stops
- 28 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 23, 2020 | Sep 29, 2020 | — |
Permit Processing Center Building Inspection · PPC | Sep 29, 2020 | Mar 15, 2023 | — |
Planning pre-screening Planning · PRE-PLN | Oct 3, 2020 | Oct 22, 2020 | — |
Zoning review Planning · CP-ZOC | Oct 23, 2020 | Oct 12, 2022 | — |
Planning neighborhood notice Planning · CP-NP | May 17, 2022 | May 20, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 12, 2022 | Feb 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Oct 12, 2022 | Jan 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 12, 2022 | Oct 21, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 21, 2022 | Feb 3, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 21, 2022 | Mar 13, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 3, 2023 | Feb 16, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 13, 2023 | Feb 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2023 | Mar 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2023 | Feb 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 15, 2023 | Mar 28, 2023 | — |
Addendum 1: Architectural, structural , t-24, mech, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 14, 2023 | Apr 14, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 14, 2023 | Aug 4, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2023 | Sep 7, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 6, 2023 | Jul 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 10, 2023 | Jul 14, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 14, 2023 | Oct 2, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 14, 2023 | Sep 14, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2023 | Oct 3, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 4, 2023 | Oct 10, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 10, 2023 | Oct 18, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 19, 2023 | Oct 20, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2023 | Feb 20, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Feb 20, 2024 | Feb 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $258,951
| Name | Role | License on permit |
|---|---|---|
| Linnea Holbrook Clark | Architect | C37079 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024