Scope of work
As written on the permit application.

Interior/exterior renovation and rear horizontal expansion of (e) 4 bedrm, 2.5 bath sfh to a 5-bedrm, 4.5 bath with a new rear deck. seismic upgrades. replace windows/doors/roof/interior stair/skylights. (n) sprinkler system under separate permit.

Timeline
Key dates from the city record.
Filed
Sep 30, 2020
Issued
Dec 14, 2021 (14 months after filing)
Completed
Oct 14, 2026 (58 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
26 stops across 5 departments
Comments issued
Not recorded for this permit
Put on hold
6 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 1, 2020—

Permit Processing Center

Building Inspection · PPC

Nov 18, 2021—

Fire pre-screening

Fire Department · PRE-FIRE

Nov 12, 2020—

Fire prevention review

Fire Department · SFFD

Nov 18, 2020—

Zoning review

Planning · CP-ZOC

May 24, 2021—

Planning neighborhood notice

Planning · CP-NP

Apr 8, 2021—

Building plan review

Building Inspection · BLDG

Sep 27, 2021—

Street use and mapping

Public Works · DPW-BSM

Oct 19, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 12, 2021—

Zoning review

Planning · CP-ZOC

Nov 18, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 27, 2021—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 27, 2021—

Central Permit Bureau

Building Inspection · CPB

Dec 14, 2021—

Addendum 1: Final plans

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 18, 2022—

Building plan review

Building Inspection · BLDG

Jun 27, 2022—

Mechanical and energy plan review

Building Inspection · MECH

May 13, 2022—

Permit Processing Center

Building Inspection · PPC

Oct 31, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 24, 2022—

Street use and mapping

Public Works · DPW-BSM

Oct 5, 2022—

Urban forestry

Public Works · DPW-BUF

Jun 14, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 5, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Oct 13, 2022—

Street use and mapping

Public Works · DPW-BSM

Oct 13, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 17, 2022—

Urban forestry

Public Works · DPW-BUF

Oct 27, 2022—

Central Permit Bureau

Building Inspection · CPB

Nov 14, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Dera-Jill Lamontagne Pozner

Pozner Architecture & Design

ArchitectC34766
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202009305567 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record