244 16th Av
San Francisco permit 202009305567 · Outer Richmond
Interior/exterior renovation and rear horizontal expansion of (e) 4 bedrm, 2.5 bath sfh to a 5-bedrm, 4.5 bath with a new rear deck. seismic upgrades. replace windows/doors/roof/interior stair/skylights. (n) sprinkler system under separate permit.
- Filed
- Sep 30, 2020
- Issued
- Dec 14, 2021 (14 months after filing)
- Completed
- Oct 14, 2026 (58 months after issuance)
- Review stops
- 26 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 30, 2020 | Oct 1, 2020 | — |
Permit Processing Center Building Inspection · PPC | Oct 1, 2020 | Nov 18, 2021 | — |
Fire pre-screening Fire Department · PRE-FIRE | Nov 10, 2020 | Nov 12, 2020 | — |
Fire prevention review Fire Department · SFFD | Nov 12, 2020 | Nov 18, 2020 | — |
Zoning review Planning · CP-ZOC | Nov 17, 2020 | May 24, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 30, 2021 | Apr 8, 2021 | — |
Building plan review Building Inspection · BLDG | May 24, 2021 | Sep 27, 2021 | — |
Street use and mapping Public Works · DPW-BSM | May 24, 2021 | Oct 19, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 24, 2021 | Jul 12, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 26, 2021 | Nov 18, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 26, 2021 | Oct 27, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 27, 2021 | Oct 27, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2021 | Dec 14, 2021 | — |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 13, 2022 | Jan 18, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 18, 2022 | Jun 27, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 18, 2022 | May 13, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 18, 2022 | Oct 31, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 19, 2022 | Feb 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 19, 2022 | Oct 5, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jan 27, 2022 | Jun 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 28, 2022 | Apr 5, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 13, 2022 | Oct 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 13, 2022 | Oct 13, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 13, 2022 | Oct 17, 2022 | — |
Urban forestry Public Works · DPW-BUF | Oct 18, 2022 | Oct 27, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 31, 2022 | Nov 14, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Dera-Jill Lamontagne Pozner Pozner Architecture & Design | Architect | C34766 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022