1045 Sansome St
San Francisco permit 202010025777 · North Beach
Add a roof terrace with outdoor seating, 42"tall guardrails set back 5' from (e) bldg parapets & new stair vestibule. demolition (e) partitions & assosciated power/data & floor finishes. construct new partitions, doors, power & tele/data, lighting, millwork & finish. 2 new restrooms.
- Filed
- Oct 2, 2020
- Issued
- Apr 12, 2022 (18 months after filing)
- Completed
- Jun 26, 2023 (14 months after issuance)
- Review stops
- 16 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 18, 2021 | Feb 18, 2021 | — |
Zoning review Planning · CP-ZOC | Feb 18, 2021 | Jul 13, 2021 | — |
Building plan review Building Inspection · BLDG | Jul 14, 2021 | Jan 25, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 19, 2021 | Feb 1, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 8, 2021 | Dec 9, 2021 | — |
Fire prevention review Fire Department · SFFD | Dec 10, 2021 | Feb 18, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 17, 2021 | Dec 21, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2021 | Mar 17, 2022 | — |
Public health review Public Health · HEALTH | Feb 1, 2022 | Feb 4, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2022 | Mar 17, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 18, 2022 | Mar 24, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 25, 2022 | Mar 25, 2022 | — |
Development fee collection Building Inspection · DFCU | Mar 25, 2022 | Mar 25, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 28, 2022 | Mar 29, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 4, 2022 | Apr 7, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 7, 2022 | Apr 12, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,400,000
| Name | Role | License on permit |
|---|---|---|
| Scott Eugene Clement Revel Architecture & Design | Architect | C36455 |
| Riley Edwards Bunn Revel Architecture & Design | Architect | C37378 |
| Ronald Owen Hamburger Simpson Gumpertz & Heger Inc | Engineer | S2951 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026