27 Christopher Dr
San Francisco permit 202010146483 · Inner Sunset
Interior renovation w/ (n) legal stair, (n) bathroom. replace (e) bathrooms, kitchen & finishes. partition reconfiguration. replace portion of hipped roof w/ continuation of (e) ridge beam & (n) gable end at rear. remove decorative railing & posts at front. replace railing & tile on (e) porch.
- Filed
- Oct 22, 2020
- Issued
- Aug 31, 2021 (10 months after filing)
- Completed
- Jan 19, 2023 (17 months after issuance)
- Review stops
- 21 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 14, 2020 | Oct 19, 2020 | — |
Permit Processing Center Building Inspection · PPC | Oct 19, 2020 | Aug 30, 2021 | — |
Zoning review Planning · CP-ZOC | Oct 27, 2020 | Jun 21, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Apr 22, 2021 | Apr 29, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2021 | Aug 20, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 21, 2021 | Jul 20, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Jun 21, 2021 | Jun 22, 2021 | — |
Zoning review Planning · CP-ZOC | Aug 19, 2021 | Aug 27, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2021 | Aug 23, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 19, 2021 | Aug 30, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Aug 30, 2021 | Aug 31, 2021 | — |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 1, 2021 | Sep 2, 2021 | — |
Building plan review Building Inspection · BLDG | Sep 2, 2021 | Oct 22, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 2, 2021 | Nov 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 2, 2021 | Sep 24, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Sep 2, 2021 | Oct 13, 2021 | — |
Permit Processing Center Building Inspection · PPC | Sep 2, 2021 | Nov 2, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 13, 2021 | Oct 15, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Oct 21, 2021 | Oct 22, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2021 | Oct 28, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2021 | Nov 4, 2021 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Michael S Warshaw Mike Warshaw Architects | Architect | C36719 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023