140 Edgehill Wy
San Francisco permit 202010176696 · West of Twin Peaks
Vertical addition to existing 2-level single-family residence. converting of (e) unconditioned storage/gym area to new one car parking garage. interior remodel with associated mechanical, electrical, plumbing work.
- Filed
- Oct 17, 2020
- Issued
- Dec 2, 2021 (14 months after filing)
- Completed
- Feb 14, 2025 (38 months after issuance)
- Review stops
- 17 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 17, 2020 | Nov 5, 2020 | — |
Zoning review Planning · CP-ZOC | Nov 6, 2020 | Jun 19, 2021 | — |
Planning neighborhood notice Planning · CP-NP | Mar 23, 2021 | Apr 12, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2021 | Oct 25, 2021 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 3, 2021 | Aug 24, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2021 | Aug 27, 2021 | — |
Permit Processing Center Building Inspection · PPC | Oct 26, 2021 | Nov 15, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Nov 15, 2021 | Dec 2, 2021 | — |
Addendum 1: Architectural, title 24, structural, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 23, 2021 | Dec 23, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 23, 2021 | Oct 7, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2022 | Nov 10, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Apr 15, 2022 | May 3, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 3, 2022 | Jan 27, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2022 | May 9, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 17, 2022 | Oct 17, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 30, 2023 | Feb 10, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2023 | Mar 22, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $750,000
| Name | Role | License on permit |
|---|---|---|
| Neal J Z Schwartz Schwartz & Architecture | Architect | C27065 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2017